Bridge deck launched for the New Wear Crossing, Sunderland (Video)

March 30, 2017

The 300m bridge deck of Sunderland’s New Wear Crossing has been successfully launched across the river.

The 4,750tonne concrete and steel deck was resting on the south side of the River Wear from where it was inched across to touch the north side in a 20-hour operation. It had to slide through the twin arched towers of the bridge’s double pylon on its way to its final position to connect the city regions of Pallion to the south and Castletown to the north.

The temporary blue steel nose will soon be removed and the remaining 40m section of deck will be built in-situ on the north side this summer.

The project to build the New Wear Crossing started in May 2015 and completion is expected in the spring of 2018. The bridge is phase two of the Sunderland Strategic Transport Corridor, which is a five-phase plan to improve links between the A19 and Sunderland City Centre and the Port of Sunderland.

Scaffolding attached to the top of the pylon will enable cable stays to be fitted, which will be attached to the deck and gradually stressed to take the weight of the bridge later this year. After that, the blue steel temporary towers supporting the deck will be removed and then lighting, road markings and safety features will be added.
Simon Fryer, a technical director of Buro Happold Engineering, who led the team that designed the bridge, said it’s been three years of hard but exciting work.

UK-based 1622 Farrans Construction and Belgian bridge specialist Victor Buck Steel Construction formed a partnership to create the FVB Joint Venture, main contractor for the bridge. FVB JV’s design team is led by Buro Happold Engineering and Roughan & O'Donovan, as well as independent checker 6801 Ramboll.

Victor Buyck Steel spent a year fabricating the pylon at its canal-side yard in Ghent. Because of its size, 8569 Sarens, a global heavy lifting and engineering transport specialist, was called in to gingerly shift the completed pylon onto two canal barges for transport along the canal to the sea port. Sarens transferred the pylon onto one, larger 100m-long seagoing barge.

When the pylon arrived about 1.5km off the coast at Sunderland, it was met by harbour tugs which brought it into port. On a specific high tide, it was carefully towed about 4.5km upriver to the site of the cofferdam between Pallion and Castletown.

The New Wear Crossing is the first bridge to be built over the River Wear in Sunderland for more than 40 years. World Highways recently featured the work as a <%$Linker:

2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 29953 0 oLinkExternal key project report Visit Key Project Report page false /categories/road-highway-structures/features/sunderlands-new-wear-crossing-takes-shape/ false false%> in the magazine and on the website.

For more information on companies in this article

Related Content

  • Almost gone: Canada’s old Port Mann Bridge deconstructed
    August 14, 2015
    Three years ago a welder’s cut halved Canada’s old Port Mann Bridge. David Arminas reports from the banks of the Fraser River. By the time this issue of World Highways reaches you, one of Canada’s iconic steel arch bridges will be a shadow of its former self. It’s been a three-year demolition job since the first cut across the deck of the old Port Mann Bridge just outside the city of Vancouver on Canada’s Pacific coast. A new 10-lane 2.2km Port Mann Bridge opened in 2012 (see box). It runs parallel to the o
  • PERI unveils VARIOKIT heavy-duty truss girder
    January 6, 2017
    PERI says that with new VARIOKIT system components it is now possible to create a heavy-duty truss girder for bridge construction. A supplement to the VARIOKIT heavy-duty shoring tower launched at bauma 2010, PERI said that during the new truss girder solution’s development it took into account load-bearing capacity of the tower and the challenging requirements of daily construction work. The modular lattice system can be used for spans up to 40m and is said by PERI to have a very high-load bearing capacity
  • PERI unveils VARIOKIT heavy-duty truss girder
    April 18, 2013
    PERI says that with new VARIOKIT system components it is now possible to create a heavy-duty truss girder for bridge construction. A supplement to the VARIOKIT heavy-duty shoring tower launched at bauma 2010, PERI said that during the new truss girder solution’s development it took into account load-bearing capacity of the tower and the challenging requirements of daily construction work. The modular lattice system can be used for spans up to 40m and is said by PERI to have a very high-load bearing capacity
  • Scotland’s Queensferry Crossing opens to traffic
    August 30, 2017
    The new Queensferry Crossing in Scotland is now open to traffic, with the first vehicles crossing at 2am this morning. The landmark design has set precedents in engineering, its three 207m high towers making it the tallest of its type in the UK and at 2.7km, also the longest three tower cable-stayed bridge built anywhere in the world. The bridge has a design life of 150 years and features two traffic lanes in either direction, as well as emergency lanes on either side. The new bridge will help reduce the ch