Bridge deck launched for the New Wear Crossing, Sunderland (Video)

March 30, 2017

The 300m bridge deck of Sunderland’s New Wear Crossing has been successfully launched across the river.

The 4,750tonne concrete and steel deck was resting on the south side of the River Wear from where it was inched across to touch the north side in a 20-hour operation. It had to slide through the twin arched towers of the bridge’s double pylon on its way to its final position to connect the city regions of Pallion to the south and Castletown to the north.

The temporary blue steel nose will soon be removed and the remaining 40m section of deck will be built in-situ on the north side this summer.

The project to build the New Wear Crossing started in May 2015 and completion is expected in the spring of 2018. The bridge is phase two of the Sunderland Strategic Transport Corridor, which is a five-phase plan to improve links between the A19 and Sunderland City Centre and the Port of Sunderland.

Scaffolding attached to the top of the pylon will enable cable stays to be fitted, which will be attached to the deck and gradually stressed to take the weight of the bridge later this year. After that, the blue steel temporary towers supporting the deck will be removed and then lighting, road markings and safety features will be added.
Simon Fryer, a technical director of Buro Happold Engineering, who led the team that designed the bridge, said it’s been three years of hard but exciting work.

UK-based 1622 Farrans Construction and Belgian bridge specialist Victor Buck Steel Construction formed a partnership to create the FVB Joint Venture, main contractor for the bridge. FVB JV’s design team is led by Buro Happold Engineering and Roughan & O'Donovan, as well as independent checker 6801 Ramboll.

Victor Buyck Steel spent a year fabricating the pylon at its canal-side yard in Ghent. Because of its size, 8569 Sarens, a global heavy lifting and engineering transport specialist, was called in to gingerly shift the completed pylon onto two canal barges for transport along the canal to the sea port. Sarens transferred the pylon onto one, larger 100m-long seagoing barge.

When the pylon arrived about 1.5km off the coast at Sunderland, it was met by harbour tugs which brought it into port. On a specific high tide, it was carefully towed about 4.5km upriver to the site of the cofferdam between Pallion and Castletown.

The New Wear Crossing is the first bridge to be built over the River Wear in Sunderland for more than 40 years. World Highways recently featured the work as a <%$Linker:

2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 29953 0 oLinkExternal key project report Visit Key Project Report page false /categories/road-highway-structures/features/sunderlands-new-wear-crossing-takes-shape/ false false%> in the magazine and on the website.

For more information on companies in this article

Related Content

  • First deck span completed for Mersey Gateway's north approach viaduct
    April 4, 2016
    The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
  • Missouri’s Blanchette Bridge gets smaller and smaller
    December 10, 2012
    Missouri’s Blanchette Bridge is now even more abridged. Just a few weeks after explosives took out the West Struss Span, the remaining steel truss on the bridge’s westbound lanes was blown up by demolition crews on Tuesday December 5, 2012. More than 2,000tonnes of steel dropped over 300m into the Missouri River. A 107m section of the Blanchette Bridge was brought down last month. The Blanchette Bridge blasting is part of a US$63 million, year-long project to replace the westbound span.
  • A free bridge? You’ve got to be kidding.
    February 18, 2015
    Nothing will stop construction of another bridge crossing the Detroit River to ease traffic congestion around North America’s most important economic border. The New International Trade Crossing will be entirely financed and owned by the Canadian government under a public private partnership. It will link the US city of Detroit, in the state of Michigan, with the Canadian city of Windsor in the province of Ontario. The two cities already have the toll road Ambassador Bridge as well as a toll road tunnel and
  • Lighter ESCO lip system offer 19% more useable wear metal
    January 6, 2017
    Wear parts specialist ESCO is using Bauma to show its new Nemisys lip system which has been engineered to deliver a lighter weight lip better sized and suited to modern buckets. The lip’s streamlined profile optimises production, says ESCO, and machine working cycles. A clever new hammerless tooth and shroud system helps reduce maintenance costs through improved reliability, faster and safer replacement, and improved lip coverage. The slim lip design and matching tooth system require 10% less force to penet