HA dismantles footbridge over M5 in England

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
January 3, 2013 Read time: 2 mins

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England.

The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane.

The dismantling and removal of the 220tonne bridge required the M5 being closed in both directions for the duration of the work, from 7pm on Saturday 10 November until around 8am the following morning, when both carriageways were fully opened.
The bridge was dismantled into two sections, each of which was hoisted and removed by cranes. This method of removal was required to avoid excessive vibration due to the presence of a pipeline on the northbound carriageway.

The new pedestrian bridge is planned to be in place and available for use by early 2013.

2309 Highways Agency project manager Paul Unwin said: “The removal of the old bridge is an essential part of the managed motorway scheme, and the closures meant that our workers were able to concentrate on doing a fantastic job in dismantling the structure as quickly and as safely as possible.”

Once completed, the €109.72 million (£88mn) managed motorway scheme will cut congestion, make journey times more reliable and improve safety through the use of variable mandatory speed limits and by opening the hard shoulder as an extra running lane. 

For more information on companies in this article

Related Content

  • Major project to construct landmark Bay Bridge in California
    October 31, 2012
    Iconic California crossing will offer seismic safety – Adrian Greeman reports A unique single-span single-tower suspension bridge is the iconic centrepiece of a dramatic renewal of the eastern Bay Bridge in California, crossing from San Francisco to Oakland. Tourists in San Francisco sometimes mix up their bridges, identifying as the famous Golden Gate, the double suspension bridge which runs across the wide San Francisco Bay. These serially linked bridges in fact form the Bay Bridge east to Oakland whereas
  • UK Highways Agency unveils additional spending plans
    April 12, 2013
    In the UKL the Highways Agency has announced plans for an additional 58 schemes intended to boost the economy, reduce congestion and improve safety. These schemes form part of the third, and final, stage of the Highways Agency’s pinch point programme. The 58 schemes represent an investment of €114.6 million (£98 million) and are intended to remove bottlenecks and keep traffic moving on England’s motorways and major A roads. They will be delivered by March 2015 and will bring an estimated €1.64 billion (£1.4
  • Another US$94.08mn for repairs to Hammersmith flyover in London
    June 14, 2013
    A further US$94.08 million (£60mn) is to be spent on fixing the Hammersmith flyover “monstrosity” in west London, England. Transport for London (TfL) is to fund a second phase of repairs to the structure’s badly corroded arches due to start in October 2013. The flyover was shut to all traffic just before Christmas 2011 to allow initial emergency arch repairs – leading to huge traffic chaos in west London – before being partially reopened a few weeks later. It was not fully opened until late May 2012.
  • Crane assembly for Tibet excavator
    February 9, 2017
    A tough machine assembly operation at extreme altitude has been carried out by two cranes from XCMG The cranes were used to assist in the assembly of a large excavator needed to assist in production at an extraction operation in Tibet. Located at an altitude of no less than 5,400m on the very remote Mila Mountain, the extraction sites was aiming at upgrading its operations and boosting productivity with the addition of a new 100tonne class excavator. The two cranes, an XCT100 model and a QAY300A machi