HA dismantles footbridge over M5 in England

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
January 3, 2013 Read time: 2 mins

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England.

The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane.

The dismantling and removal of the 220tonne bridge required the M5 being closed in both directions for the duration of the work, from 7pm on Saturday 10 November until around 8am the following morning, when both carriageways were fully opened.
The bridge was dismantled into two sections, each of which was hoisted and removed by cranes. This method of removal was required to avoid excessive vibration due to the presence of a pipeline on the northbound carriageway.

The new pedestrian bridge is planned to be in place and available for use by early 2013.

2309 Highways Agency project manager Paul Unwin said: “The removal of the old bridge is an essential part of the managed motorway scheme, and the closures meant that our workers were able to concentrate on doing a fantastic job in dismantling the structure as quickly and as safely as possible.”

Once completed, the €109.72 million (£88mn) managed motorway scheme will cut congestion, make journey times more reliable and improve safety through the use of variable mandatory speed limits and by opening the hard shoulder as an extra running lane. 

For more information on companies in this article

Related Content

  • Tunnel project of Chilean capital Santiago
    April 8, 2015
    Tunnel construction in Chilean capital Santiago will help cut chronic congestion – Mauro Nogarin & Mike Woof write. Chile’s capital Santiago is a thriving city having benefited from the country’s economy growing strongly in recent years. The massive copper mining sector has helped boost the country’s GDP significantly in the past few decades, also aided by the growing international reputation of Chile’s large wine industry. The steady economic growth has resulted in an equally steady growth in average incom
  • A30 Cornwall upgrade nears finishing line
    May 30, 2025
    Trevalso underpass to open by early summer
  • Lindsay Transport’s Road Zipper at Hirschstetten and Stadlau Tunnels
    July 5, 2016
    Lindsay Transportation Solutions recently used the Intertraffic exhibition in Amsterdam to highlight a major deployment of its Road Zipper System in Austria Work is underway in Vienna to rehabilitate two ageing tunnels and the asphalt highway sections that connect them – a major route into and out of the Austrian capital Vienna. Tunnels, like bridges, offer additional challenges for road works. Typically, there is very little additional space and a work zone must be created from active traffic lanes. The
  • Caterpillar adds to its rollcall of rollers with the CB13, 15, 16
    May 15, 2018
    All three of Caterpillar’s newest production class tandem vibratory rollers models can be equipped with an oscillatory vibration system. The new models - CB13, CB15, and CB16, designated according to operating weigh – also offer refinements to the operator controls, water spray system, service access and lighting packages.