HA dismantles footbridge over M5 in England

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
January 3, 2013 Read time: 2 mins

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England.

The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane.

The dismantling and removal of the 220tonne bridge required the M5 being closed in both directions for the duration of the work, from 7pm on Saturday 10 November until around 8am the following morning, when both carriageways were fully opened.
The bridge was dismantled into two sections, each of which was hoisted and removed by cranes. This method of removal was required to avoid excessive vibration due to the presence of a pipeline on the northbound carriageway.

The new pedestrian bridge is planned to be in place and available for use by early 2013.

2309 Highways Agency project manager Paul Unwin said: “The removal of the old bridge is an essential part of the managed motorway scheme, and the closures meant that our workers were able to concentrate on doing a fantastic job in dismantling the structure as quickly and as safely as possible.”

Once completed, the €109.72 million (£88mn) managed motorway scheme will cut congestion, make journey times more reliable and improve safety through the use of variable mandatory speed limits and by opening the hard shoulder as an extra running lane. 

For more information on companies in this article

Related Content

  • Highways Agency rebrands as part of its first five-year plan
    December 10, 2014
    The UK’s Highways Agency will rebrand as part of the organisation’s first five-year Strategic Business Plan to maintain England’s motorways and major A roads up to 2020. The plan for England’s strategic road network was developed response to the Road Investment Strategy published in early December. The UK government is getting set to make deliver the largest investment in roads since the 1970s and wants to make sure it gets value for money as well as nearly US$1.9 billion (£1.2 billion) of efficiency savin
  • UK to cut down on “disruptive roadworks”
    January 15, 2024
    The announcement comes today, on the UK’s annual so-called National Pothole Day.
  • Rebuilding a critical transportation artery in Italy
    September 7, 2020
    Software from Bentley Systems has played an important role in the Morandi Bridge replacement project
  • 2010 GRAA Winner Profiles
    February 13, 2012
    Our series of profiles on winning projects from the 2010 Global Road Achievement (GRAA) Awards continues with the Construction Methodology Category won by Barrier Systems/Utah Department of Transportation With any major road construction project, the disruption of traffic flow is of paramount concern for engineers, workers and travellers, particularly as it relates to increased traffic delays and the safety of those driving through the work zone.