HA dismantles footbridge over M5 in England

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
January 3, 2013 Read time: 2 mins

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England.

The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane.

The dismantling and removal of the 220tonne bridge required the M5 being closed in both directions for the duration of the work, from 7pm on Saturday 10 November until around 8am the following morning, when both carriageways were fully opened.
The bridge was dismantled into two sections, each of which was hoisted and removed by cranes. This method of removal was required to avoid excessive vibration due to the presence of a pipeline on the northbound carriageway.

The new pedestrian bridge is planned to be in place and available for use by early 2013.

2309 Highways Agency project manager Paul Unwin said: “The removal of the old bridge is an essential part of the managed motorway scheme, and the closures meant that our workers were able to concentrate on doing a fantastic job in dismantling the structure as quickly and as safely as possible.”

Once completed, the €109.72 million (£88mn) managed motorway scheme will cut congestion, make journey times more reliable and improve safety through the use of variable mandatory speed limits and by opening the hard shoulder as an extra running lane. 

For more information on companies in this article

Related Content

  • George Massey Tunnel Replacement gets environmental approval
    February 13, 2017
    The Canadian province of British Columbia has given environmental approval for a 10-lane US$2.8 billion bridge to replace the ageing George Massey Tunnel near Vancouver. However, approval for the 3km cable stay bridge over the Fraser River comes with 33 conditions, according to Canadian media. Construction of the toll bridge will also mean replacing the interchanges of Westminster Highway, Steveston Highway and Highway 17A.
  • Crane collapse on US bridge project
    July 20, 2016
    A crane collapsed over the Tappan Zee Bridge in the US on July 19th. Construction work is being carried out on the bridge. The structure is located in Tarrytown, New York State and the bridge is around 40km north of central Manhattan, spanning the Hudson River at one of its widest points. The crane was being used for the construction work and collapsed right across the roadway and in front of vehicles using the crossing. A number of vehicles were damaged in the incident and local news reports suggest up to
  • M27 contract for McCann
    July 29, 2020
    Highways England has awarded an M27 contract to McCann.
  • Concerns over increased US road fatality rate in 2012
    November 25, 2013
    Data from the US Department of Transportation's National Highway Traffic Safety Administration (NHTSA) shows that highway deaths increased to 33,561 in 2012, an increase of 1,082 over the figures for 2011.The official Fatality Analysis Reporting System (FARS) data reveals that the majority of the increase in deaths, some 72%, occurred in the first quarter of 2012. Most of those involved were motorcyclists and pedestrians. This newly released data marks the first increase in road related fatalities in the US