Climbing in Corpus Christi

The challenge for Doka on the new Harbor Bridge in Texas was to use the same formwork for each pylon despite each pylon’s different geometry.
September 17, 2020 Read time: 2 mins
Doka used its hydraulic climbing formworks SKE50 and SKE100 plus its large-area formwork Top 50

The new US 181 Harbor Bridge is being constructed to replace an ageing bridge across the Corpus Christi Ship Channel off the Gulf of Mexico. The replacement bridge, with nearly a 63m clearance, will also allow the passage of larger ships and possibly cruise ships into the docks. The current Harbor Bridge was opened in 1956 to replace a drawbridge and now handles 26,000 vehicles per day. When complete, the new Harbor Bridge will be the tallest point in southern Texas and the longest cable-stayed concrete segmental bridge in the US.

The upper and lower pylons were different shapes requiring two designs. The primary pylon structures have a geometry that narrows and angles at the same time. A reusable system was needed that would have minimal changes between pours.

Doka used large-area formwork Top 50 as well as hydraulic climbing formwork SKE50 and SKE100 platforms. The system was designed with telescopic platforms that adjust to the changing pylon shape. Doka says there were almost 520m² of formwork for one pylon.

Doka helped the contractor – a Flatiron and Dragados joint venture - remain on schedule because there was minimal rebuild between pours. Doka also saved crane time due to the hydraulic lifting systems employed.

The contract won by Flatiron and Dragados includes $854.6 million for design and construction of the bridge and another $128.2 million for the 25-year maintenance and operation of the bridge.

For more information on companies in this article

Related Content

  • Scotland’s new Queensferry Crossing over the Forth Estuary
    December 23, 2015
    The new Queensferry Crossing under construction in Scotland will be the third landmark bridge spanning the Forth Estuary - Mike Woof writes When the new Queensferry Crossing over the Forth Estuary opens at the end of 2016, it will be the third landmark bridge to be built spanning this short stretch of water. Lying alongside the existing road bridge and the historic rail bridge, this new structure will be as groundbreaking as the two earlier crossings were at the time of their construction.
  • Ambitious road tunnelling projects around the world
    November 29, 2013
    The construction of the world’s longest subsea road tunnel in Norway and a vital new link under the Bosphorus Strait in Turkey are among a host of exciting, major road tunnel-based projects currently being undertaken across the globe. Guy Woodford reports Sandvik DTi series tunnelling jumbos are being used for the excavation of Solbakktunnel, set to become the world’s longest subsea road tunnel.
  • New bridge is spanning China’s Yangtze River
    June 28, 2013
    There is massive development in design and construction of bridges in China and the Yingwuzhou Bridge over the Yangtze River is one key project – Mike Woof reports, with assistance from Route One’s Chinese publishing partner *CMTM Called the Mother River, the Yangtze is a focal point for China politically, economically and culturally. The river has been at the heart of China’s development for millennia, its history stretching back as far as the dawn of human civilisation. The name Yangtze, or Yangzi, is its
  • Bridge project uses high performing formwork
    February 20, 2012
    Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle. The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.