The challenge for Doka on the new Harbor Bridge in Texas was to use the same formwork for each pylon despite each pylon’s different geometry.
September 17, 2020 Read time: 2 mins
Doka used its hydraulic climbing formworks SKE50 and SKE100 plus its large-area formwork Top 50

The new US 181 Harbor Bridge is being constructed to replace an ageing bridge across the Corpus Christi Ship Channel off the Gulf of Mexico. The replacement bridge, with nearly a 63m clearance, will also allow the passage of larger ships and possibly cruise ships into the docks. The current Harbor Bridge was opened in 1956 to replace a drawbridge and now handles 26,000 vehicles per day. When complete, the new Harbor Bridge will be the tallest point in southern Texas and the longest cable-stayed concrete segmental bridge in the US.

The upper and lower pylons were different shapes requiring two designs. The primary pylon structures have a geometry that narrows and angles at the same time. A reusable system was needed that would have minimal changes between pours.

Doka used large-area formwork Top 50 as well as hydraulic climbing formwork SKE50 and SKE100 platforms. The system was designed with telescopic platforms that adjust to the changing pylon shape. Doka says there were almost 520m² of formwork for one pylon.

Doka helped the contractor – a Flatiron and Dragados joint venture - remain on schedule because there was minimal rebuild between pours. Doka also saved crane time due to the hydraulic lifting systems employed.

The contract won by Flatiron and Dragados includes $854.6 million for design and construction of the bridge and another $128.2 million for the 25-year maintenance and operation of the bridge.

For more information on companies in this article

Related Content

  • On track with Doka – Çanakkale 1915 Bridge takes shape
    October 1, 2021
    Since delivering an engineering solution for the monumental Çanakkale 1915 Bridge, Doka Turkey has continued its work on this record-breaking project as it takes another step towards its scheduled completion, in time for the country’s centennial in 2023
  • Bridge formwork solutions complete big bridge picture
    July 2, 2014
    Advanced bridge formwork solutions are allowing contractors to complete vital major highway infrastructure projects covering Norway, Sweden, Estonia and Poland. Guy Woodford reports Building the Labbdalen bridges in Norway is a key feature of the E6 highway improvement programme. Main project contractor HÆHRE tasked RMD Kwikform and Teknikk with supplying a complete formwork and shoring solution that could tackle the challenging Norwegian terrain, whilst preserving the environment. Situated two hours
  • Cable works starts on Gordie Howe Bridge
    February 10, 2023
    The tolled six-lane bridge over the Detroit River, between Windsor in Canada and Detroit in the US, is costing around US$4.2 billion with an opening date likely in 2025.
  • Storstrom Bridge to be Denmark’s third longest
    March 8, 2018
    Form and functionality come together in Denmark’s latest Storstrom Bridge design. David Arminas reports. An Italian joint venture recently won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The Danish Road Directorate - Vejdirektoratet - awarded the work to a joint venture of Condotte and Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 milli