Sunderland’s sliding bridge slips across the Wear

Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation next year likely. The project to build the New Wear Crossing is now half way through with the first half of the steel deck bridge poised mid-river. Completion of the bridge is expected in the spring of 2018. This month, hydraulic jack
October 26, 2016 Read time: 2 mins
Sunderland’s new bridge slides into existence
Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation next year likely.

The project to build the New Wear Crossing is now half way through with the first half of the steel deck bridge poised mid-river. Completion of the bridge is expected in the spring of 2018.

This month, hydraulic jacks slowly pulled the first deck section – a 230m long steel structure – around 120m out across the water during a seven-hour operation. Time-lapse photography shows construction of the deck and %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal its eventual launch Visit www.sunderland.gov.uk website false http://www.sunderland.gov.uk/index.aspx?articleid=11787 false false%>.

The deck is being held in place above the water on a series of temporary supports constructed within the riverbed. This enables assembly of the second section of bridge deck directly behind the first on the south side of the river.

Once the 105m high A-frame pylon, which is the centrepiece of the bridge, arrives on site early in 2017 and is raised into position, the extended bridge deck will then be pulled into position across the width of the river.

The permanent deck is 186m long and the temporary ‘nose’ - used to allow the deck to land on the temporary supports - is 37m long. The temporary ‘tail’ that connects the jacking system to the deck is 7m long.

Of the section’s 2,500 tonnes, around 1,350 tonnes consists of 212 precast concrete units that will form the road bed.

A further 256 concrete units, weighing 1,600 tonnes, will be added to the bridge deck before the next launch across the River Wear. The remaining 172 concrete panels will then be installed after the bridge deck is in its final position.

An artist’s impression of the full construction process is available %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal Sunderland City&#8217;s website Visit YouTube page false http://www.youtube.com/watch?v=u6-jBoa3f74 false false%>.

The project is on schedule, said Stephen McCaffrey, project director of the FVB joint venture, formed by Farrans Construction and Belgium-based Victor Buyck Steel Construction which is delivering the project on behalf of Sunderland City Council.

FVB JV will be supported by their design team led by Buro Happold Engineering as well as Roughan & O'Donovan.

Related Content

  • UK: Work starts on Mersey Gateway main bridge deck
    June 2, 2016
    Work has started on 2.2km Mersey Gateway’s main bridge deck as the project enters its third year of construction. The new six-lane toll bridge will link the English towns of Runcorn and Widnes and teams will begin to connect the steel support cables to the deck and upper pylons this summer. Trinity, the project’s movable scaffolding system (MSS), has cast the first 250m of the north approach viaduct and a new MSS is on its way to Halton to build the south approach viaduct. The local road network is al
  • Uzbekistan targets of 2,700km of new highways by 2019
    September 30, 2015
    Uzbekistan plans to build around 2,700km of roads by 2019 at a cost of around US$590 million. Around 2,280km will have a bituminous concrete surface and 418km will be a concrete surface. In July, the World Bank said it will grant Uzbekistan a $200 million loan for 25 years towards paying for the $240 million Regional Roads Development project that is scheduled to be completed by 2021, according to UzDaily.uz. Uzbekistan’s government also reported that around 117km roads were built in the first half
  • World Bank finances Uzbekistan road development
    July 7, 2015
    The World Bank will grant Uzbekistan a US$200 million loan for 25 years, including a grace period of five years. The funds will go towards the $240 million Regional Roads Development project that is scheduled to be completed by 2021, according to UzDaily.uz. Uzbekistan’s government also reported that around 117km roads were built in the first half of this year.
  • VIDEO: camper trailer and snowmobile takes to a frozen lake
    February 22, 2016
    Canadian love their ice fishing, but sometimes it gets just a little chilly out there on a windswept lake, especially when it is already -20C with no wind-chill factored in. Some people have tents and some have small portable protective huts big enough for one person. But there is a better way to head out across a frozen lake, as this do-it-yourself ice fisherman shows.