Sunderland’s sliding bridge slips across the Wear

Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation next year likely. The project to build the New Wear Crossing is now half way through with the first half of the steel deck bridge poised mid-river. Completion of the bridge is expected in the spring of 2018. This month, hydraulic jack
October 26, 2016 Read time: 2 mins
Sunderland’s new bridge slides into existence
Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation next year likely.

The project to build the New Wear Crossing is now half way through with the first half of the steel deck bridge poised mid-river. Completion of the bridge is expected in the spring of 2018.

This month, hydraulic jacks slowly pulled the first deck section – a 230m long steel structure – around 120m out across the water during a seven-hour operation. Time-lapse photography shows construction of the deck and %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal its eventual launch Visit www.sunderland.gov.uk website false http://www.sunderland.gov.uk/index.aspx?articleid=11787 false false%>.

The deck is being held in place above the water on a series of temporary supports constructed within the riverbed. This enables assembly of the second section of bridge deck directly behind the first on the south side of the river.

Once the 105m high A-frame pylon, which is the centrepiece of the bridge, arrives on site early in 2017 and is raised into position, the extended bridge deck will then be pulled into position across the width of the river.

The permanent deck is 186m long and the temporary ‘nose’ - used to allow the deck to land on the temporary supports - is 37m long. The temporary ‘tail’ that connects the jacking system to the deck is 7m long.

Of the section’s 2,500 tonnes, around 1,350 tonnes consists of 212 precast concrete units that will form the road bed.

A further 256 concrete units, weighing 1,600 tonnes, will be added to the bridge deck before the next launch across the River Wear. The remaining 172 concrete panels will then be installed after the bridge deck is in its final position.

An artist’s impression of the full construction process is available %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal Sunderland City&#8217;s website Visit YouTube page false http://www.youtube.com/watch?v=u6-jBoa3f74 false false%>.

The project is on schedule, said Stephen McCaffrey, project director of the FVB joint venture, formed by Farrans Construction and Belgium-based Victor Buyck Steel Construction which is delivering the project on behalf of Sunderland City Council.

FVB JV will be supported by their design team led by Buro Happold Engineering as well as Roughan & O'Donovan.

Related Content

  • Consortia line up for Denmark’s Storstrom Bridge project
    February 12, 2015
    Samsung, Daewoo, Hyundai, Acciona, Ed Züblin, MT Højgaard and Per Aarsleff are among the bidders to build a bridge connecting the Danish islands of Zealand and Falstser. The Danish Road Directorate expects to choose five pre-qualified consortia for the Storstrom Bridge project in May and the bids for the project are scheduled to be submitted by April 2016. The new bridge, likely to cost around €565 million including the cost of demolishing the old bridge it will replace, is expected to open by 2021, a
  • NDT sensor fusion in structural pavement condition surveys
    February 27, 2017
    Early detection of pavement defects and the causes of deterioration is essential for effective maintenance planning, writes Dr Alena Uus* There is a need for optimisation and development of UK highway survey methods that would provide comprehensive information on the surface and subsurface pavement condition and operate at traffic speed, which eliminates the requirement for lane closures. Performance of non-destructive testing (NDT) methods commonly employed in pavement condition surveys can be potent
  • VIDEO: Wheel loaders turn on each other in Chinese street battle
    April 19, 2016
    Irate Chinese construction workers decided enough was enough and took to the streets to settle their turf war, caught on video by a bystander. At one point, a wheel loader is seen charging in from the left, coming to the rescue of his overturned fellow loader. He almost rights the stricken machine that is lying on its side. After the dust had settle, their site managers might have had something to say about their use of company equipment. So where exactly to old dozers go to die? Are they carted of
  • Tunnel development set for Englischer Garten in Munich, Germany
    December 7, 2016
    The German state of Bavaria will invest around €35 million in a road tunnel under the Englischer Garten in Munich. The city of Munich will have to find the rest of the expected €125 million construction cost for the 380m tunnel that will replace a motorway that splits the park. German media reports say that city authorities will look toward some form of private sponsorship for tunnel that would likely be a cut and cover design that would follow closely the current alignment of the highway. Englisch