Slovakia’s troubled D1 highway

Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.
February 20, 2012 Read time: 2 mins
2875 Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.

The move towards state funding is a major change in policy as the highway was originally planned to be paid for through a PPP by the Slovenske Dialnice consortium, which had won the concession for the project.

However, the deal was cancelled and Slovenske Dialnice has said it will dispute a €10 million fine being imposed by the Ministry for allegedly not being able to secure finance for the construction and operation of the Martin-Presov section.

Slovak construction firm 2877 Doprastav, which was part of the Slovenske Dialnice consortium, said that it secured finance worth €1.66 billion from 18 commercial banks. Of this, €1 billion was from the 1054 European Investment Bank (EIB); €190 million from the 1166 European Bank for Reconstruction and Development (EBRD) and €379 million from other sources. The total finances available for the project totalled €3.23 billion, which was sufficient for the project, according to Doprastav.

The construction companies claim the project failed due to objections stemming from environmental groups, for which the government is responsible, and the EIB and EBRD expressed concern over the D1 project when the environmental issues were revealed.

Questions were raised regarding the legality of the environmental impact assessment, which resulted in the project being scrutinised by the 2465 European Commission. After this the EIB and EBRD showed reservations as pushing ahead with the project as it stood could end in a legal tangle at the European Court of Justice.

Following elections in Slovakia a new administration took power and announced its concern over the cost of the D1 project, although the consortium did manage to reduce the budget required for the work by addressing bank interest charges. Responsibility for the original environmental impact assessment may prove to be the key to this complex legal tangle.

Related Content

  • €180 million for Bosnia highway
    July 6, 2012
    The EBRD is investing in the largest infrastructure project in Bosnia-Herzegovina (BiH) to date by lending €180 million to the state to construct key sections of the Trans-European Corridor Vc. A key transport artery linking BiH with the rest of Europe, Corridor Vc starts in Budapest, Hungary and ends in the Adriatic Port of Ploce in Croatia. It runs north to south through the centre of BiH, and is the most strategically important link for regional trade and economic development. The €180 million EBRD finan
  • Slovakia: early 2017 restart for work on the Cebrat Tunnel
    May 27, 2016
    Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn
  • Slovakian highways are priority routes for Europe?
    May 5, 2016
    Slovakia is looking to benefit from European funding for key highway projects. The country’s Transport Ministry has selected a number of expressway projects as well as the D1 and D3 highways as being of high priority.
  • Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section
    December 13, 2017
    Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the