Slovakia's D1 highway moving ahead

Slovakia's Transport Ministry has been working with highway firm NDS on a highway construction programme for the 2011-2014 period.
March 1, 2012 Read time: 1 min
Slovakia's Transport Ministry has been working with highway firm NDS on a highway construction programme for the 2011-2014 period. The programme calls for five tenders for five sections of the D1 highway. These five sections were part of the PPP project for the D1 highway, which was cancelled due to funding issues. Construction work on the Dubna Skala-Turany, Turany-Hubova, Hubova-Ivachnova, Janovce-Jablonov and Fricovce-Svinia stages of the D1 will start from the middle of this year through to the second quarter of 2012. In all these sections will total 75km and are due for completion in 2013-2015.

The tender for the 11.2km stage of the D1 from Fricovce-Svinia is open and is expected to cost €213.2 million, while the work will take three years to complete. Funding will be provided by the 3287 EU Cohesion Fund and the government budget funds within the Operational Programme Transport. Slovakia's Transport Ministry hopes to open the Turany-Hubova section of the D1 highway by 2015. The Transport Ministry has said that Slovakia will meet criteria for EU funding for the project in spring 2011.

For more information on companies in this article

Related Content

  • Important road works for Slovakia
    July 6, 2023
    Important road connection works are underway for Slovakia.
  • Go-ahead for controversial highway
    May 30, 2012
    APPROVAL HAS now been given for work to go ahead on a key section of Slovakia’s D1 highway. The work had been delayed as the European Commission (EC) was concerned over environmental issues facing sections of the route that passed through a nature reserve. The EC has now given its approval for construction of the highway between Martin and Presov on conditional terms. The EC says that the sections in zones belonging to the Natura 2000 network can be built once terms are agreed with the Slovak government o
  • Slovakia keeps to planned D1 Hubova-Ivachnova completion date
    August 19, 2019
    Slovakia’s national motorway company NDS has confirmed the D1 motorway between Hubova and Ivachnova is on schedule to be completed by mid-2022. Work on the 15km stretch of road – effectively a bypass for the town of Ruzomberok –was started in 2013. But a major landslide in 2015 halted work, pushing back completion from 2017 to 2022 at the latest estimate. Montenegrin media report that the cost of the project has grown from €227 million in 2013 to nearly €289 million. Construction is being carried out
  • Slovakia opens Levoca bypass of D1 motorway section
    December 4, 2015
    Slovakia has opened the 9.5km Levoca bypass, nearly completing the northern part of the D1 cross-country motorway. The remaining section between Bratislava and Kosice is expected to be open around 2020, with the Zilina, Presov and Ruzomberok bypasses yet to be built. The newly opened section of Janovce - Jablonov II includes the 600m tunnel Sibenik, as well as a slip road to Levoca and 12 road bridges. Construction works on the D1 section started in June 2012 by the consortium of Eurovia and Stavby M