Severn Bridge to have weight restrictions

The restrictions start May 27 when heavy goods vehicles must use the nearby cable-stayed M4 motorway Prince of Wales Bridge between England and Wales.
By David Arminas April 15, 2025 Read time: 2 mins
Since the bridge opened nearly 60 years ago, the size and weight of heavy goods vehicles have increased significantly, some increasing rising from 22 tonnes to 44 tonnes (image courtesy National Highways)

England’s road agency National Highways is introducing a 7.5 tonne weight limit for vehicles using the Severn Bridge after inspections showed deterioration to the supporting cables.

The suspension Severn Bridge, which opened in 1966, carries the M48 motorway over the Severn River which separates England and Wales. National Highways said there has been concern about the state of the cables since inspections in 2022 and 2023. Further laboratory testing has revealed that the main cables are deteriorating.

The weight restrictions come into force May 27 which means heavy goods vehicles will have to use the nearby 30-year-old cable-stayed M4 motorway Prince of Wales Bridge to travel between England and Wales. The weight restriction will remain in place for an estimated 12 to 18 months, depending on further investigations and while National Highways develops and installs a medium-term solution.

National Highways also said that it is considering installing automatic number plate recognition (APNR) to support enforcement of the new weight restriction.

According to the road agency, the weight restriction will remain in place for 12 to 18 months, depending on further investigations and while National Highways develops and installs a medium-term solution.

“While the bridge remains safe, it was not designed and built for today’s levels or weight of traffic,” said Chris Pope, programme delivery manager for National Highways. “Vehicles have got heavier and traffic levels have increased significantly over the last 60 years putting greater load on the cables. “As with all our structures, we will continue to monitor the bridge and ensure it remains safe for users.”

The Severn Bridge carried around 32,000 vehicles daily in 2024, 3,270 of which were heavy goods vehicles over 7.5 tonnes, meaning around 10 percent of traffic will be diverted via the M4 Prince of Wales Bridge once the restrictions are in place.

The size and weight of heavy goods vehicles - trucks - have increased significantly due to evolving transport demands, some rising from 22 tonnes to 44 tonnes. Since the tolls were removed on the bridge in 2018 there has been a 34% increase in traffic and these changes mean a substantial increase in weight over the bridge, for which it was not designed, noted National Highways.
 

For more information on companies in this article

Related Content

  • Vitronic’s 90 POLISCAN for Maryland
    November 16, 2022
    Conduent Transportation, a provider of automated transportation solutions, will use Vitronic’s LIDAR-based speed enforcement technology to improve road safety in the US state of Maryland.
  • Highways England to trial different speeds through road works
    August 6, 2018
    Highways England is trialling different speed limits through roadworks during different times in order to respond to drivers’ feedback. Highways England, the government-owned company responsible for modernising, maintaining and operating England’s motorways and major A roads, said it is acting on drivers’ frustration with roadworks. Speed through motorway roadworks could be increased depending on what day of the week they are travelling. The decision follows earlier trials to increase the speed l
  • Busy bridge in Beijing replaced quickly
    March 31, 2016
    The replacement of a very busy road bridge in China’s capital Beijing has been carried out successfully. Due to the volume of traffic using the bridge during week days, the work had to be carried out quickly so as to minimise traffic disruption. But despite being carried out in the centre of Beijing, the replacement work for the Sanyuan Bridge just took 43 hours from start to completion.
  • Pandemic impact on Wacker Neuson results
    November 6, 2020
    The pandemic is having an impact on Wacker Neuson’s results.