Renfrew Bridge opening tests complete

The 184m-long cable-stay bridge near Glasgow, Scotland, will be the first road bridge across the River Clyde to open for passing ships.
By David Arminas August 28, 2024 Read time: 2 mins
The cable stay system is similar to Scotland’s Queensferry Crossing bridge - a twin-leaf design with each leaf opening and closing horizontally (image courtesy Graham Construction)

The first operational working of the Renfrew Bridge near Glasgow, Scotland has been accomplished ahead of the bridge opening by the end of this year.

Main contractor Graham said it will continue commissioning works for the bridge that will be the first road bridge across the River Clyde to open for passing ships. The 184m-long cable-stay two-lane road bridge will carry vehicles, pedestrians and cyclists between Glasgow and West Dunbartonshire.

The cable stay system is similar to the Queensferry Crossing - a twin-leaf design with each leaf opening and closing horizontally. Most commercial ships travel on the river during high tide, which happens once during the day and once during the night. When this happens, the bridge will be closed to road traffic, with signs nearby and information online providing advance notice of any closure to all people to plan ahead.

There will be new walking and cycling routes alongside all new roads through Renfrew and across the bridge.

The bridge is central to the major Clyde Waterfront and Renfrew Riverside redevelopment. “It was great to see the bridge closing for the first time in such a smooth, controlled and seamless operation,” said Jim Armour, project director at Graham, a privately-owned national construction company with a €1.32 billion turnover.

The two sections of the bridge were manufactured in the Netherlands and barged over, passing up the English Channel and then up the Irish sea to the site earlier this year.

The project is jointly funded by the UK and Scottish governments through the €1.32 billion Glasgow City Region, a partnership of eight councils working together.

For more information on companies in this article

Related Content

  • Canadian tower tops out on Gordie Howe
    December 21, 2023
    The six-lane cable-stayed bridge project includes new customs plazas in both Detroit and Windsor as well as a new link to the I-75 interstate highway in Detroit.
  • More tenders for Lower Thames Crossing
    April 1, 2021
    The winners will build 23km of road connecting to the UK’s longest road tunnel.
  • Russia to commission new Moscow-St Petersburg highway by 2020
    June 20, 2017
    Final delivery of the final stretch for Russia’s key highway project looks set to be delayed – Eugene Gerden writes. I now looks as if Russia’s most ambitious project in the field of road building in recent years, the building of a new high-speed road link between Moscow and St Petersburg, the country’s largest cities, will not be complete in time. The project was set up by the Russian government and several private investors. According to initial state plans, building of the new road should have been compl
  • Montreal’s new Champlain Bridge is in a race against time
    June 8, 2018
    Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General. The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path. The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate. The government signed a contract in 2015 with a private