PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Duisburg double for lift specialist Sarens
    June 5, 2024
    Heavy lift specialist Sarens overcame challenging wind and water conditions during installation of two strategic road bridges - the Oberbürgermeister Karl Lehr Brücke and the Hafenkanalbrücke - in the German city of Duisburg.
  • Bolivia’s new highway
    October 10, 2017
    Bolivia’s new highway will provide better access into mountain areas – Mauro Nogarin writes At the beginning of 2015, work began on the construction and paving for the Tupiza - Atocha - Uyuni highway project. The route is located in Bolivia’s Potosí department: it is 189m in length and forms part of the Southwest Basic Road Network (RVF) of Bolivia. The completion of this important route is requiring funding worth US$150 million, of which 72% is being delivered through loans from the European Investment
  • Challenging tunnel conditions in Germany
    June 30, 2020
    Construction of the new German A44 route, linking the A7 near Kassel to the A4 near Herleshausen, is a challenging project.
  • Republic of Ireland’s N25 New Ross Bypass achieves financial close
    March 3, 2016
    The €230 million N25 New Ross Bypass public-private partnership (PPP) project in County Wexford, Republic of Ireland has reached financial close. Mott MacDonald is technical advisor on the public-private partnership, awarded by the National Roads Authority, otherwise known as Transport Infrastructure Ireland. Work will be carried out by BAM Ireland and Dragados, a construction division of ACS Group, based in Spain. The scheme involves construction of 13.6km of dual carriageway and 1.2km of new or u