Polish debut

PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Cranes help construct major bridge project in CHina
    September 8, 2014
    A number of tower cranes have helped complete the Chishi Grand Bridge project in China Six Potain tower cranes were used to build two 280m tall bridge pylons, high in the clouds above the mountains of southern China. The cranes spent 30 months building the pylons at the Chishi Grand Bridge, which will span 1.47km and carry its road deck 180m above the ground. The bridge will open at the end of 2014.
  • Optimising Specialist Bitumen Handling with the MEST Bitutainer™
    June 1, 2025

    As roads become more advanced and surface performance expectations rise, traditional hot bitumen is no longer the only material in demand. Across the globe, highways projects are increasingly relying on high-performance binders, from polymer-modified bitumen (PMBs) to specialist emulsions and tack coats designed for specific temperature conditions or traffic volumes.

  • Asphalt and bitumen - testing for performance
    February 29, 2012
    The stresses placed on modern asphalt and bitumen means that specialist equipment is essential to make sure performance specifications are met. As road traffic increases at a rapid pace and road safety becomes a priority issue, asphalt is put under increasingly higher stresses. For example, road surfaces are subject to compression, flexural tensions and tangential stresses: internal friction, depending on the aggregates, and the cohesion, guaranteed by bitumen's composition, are the two main properties whic
  • Volvo CE moves on carbon reduction
    September 30, 2022
    David Arminas asks why Volvo Construction Equipment recently exhibited at MOVE, a major London urban mobility exhibition. Mats Bredborg explains it all