Pattullo Bridge deck near completion

For several weeks, crews have been installing concrete deck panels, steel girders and stay cables outward from the towers of the bridge that spans the Fraser River near Vancouver, Canada.
By David Arminas July 29, 2025 Read time: 2 mins
Crews are working on bridge finishes, including fencing, utilities, barriers and expansion joint installation, which will be followed by asphalt paving later this summer (image courtesy Transportation Investment Corporation/Partnerships British Columbia)

Deck panel installation for the US$1.03 billion Pattullo Suspension Bridge replacement project in the Vancouver area is nearing completion, with concrete pours being planned.

The bridge crosses the Fraser River and links the cities of New Westminster and Surrey in Metro Vancouver,

For several weeks, crews have been installing concrete deck panels, steel girders and stay cables outward from the bridge tower. The connection of the south approach and main span was recently completed, marking the creation of a continuous bridge deck from the bridge tower into Surrey.

Crews are working on bridge finishes, including fencing, utilities, barriers and expansion joint installation, which will be followed by asphalt paving later this summer.

When the four-lane toll-free bridge opens this autumn, the existing 1.3km-long four-lane old bridge will be removed. The bridge was opened in 1937 and had no median space between the opposing traffic flow, leading to many head-on crashes.

Fraser Crossing Partners – a joint partnership between Acciona Infrastructure Canada and Aecon Group – have designed and are constructing the bridge. The contract includes construction of road connections at the bridgeheads in New Westminster and Surrey. Its will include pedestrian access and allow for future widening from four to six lanes.

Construction of the new bridge was expected to take place between 2019 and 2023, with the CAN$1.3 billion funding finalised in 2018. However, work started at the beginning of the pandemic, in February 2020. According to the provincial British Columbia government, the project has faced significant challenges, including inflationary pressures and global supply issues related to the delivery of specialised components from around the world. In addition, the bridge tower construction took longer than expected, pushing back the completion date.

The official name of the bridge has yet to be decided, but the name will be in Halkomelem, the language of the local First Nations people upon whose land the bridge stands. The name will be decided jointly by Musqueam First Nation and Kwantlen First Nation groups.

The new bridge is funded and owned by the province of BC while the Transportation Investment Corporation (TI Corp) is responsible for managing the delivery of the Project. The BC Ministry of Transportation and Infrastructure will be responsible for, and maintain, the new bridge once completed.

For Videos and images of construction progress, click here.

For more information on companies in this article

Related Content

  • East End Crossing Project—Availability payment P3 in action
    July 14, 2017
    Indiana exercised its authority to use a P3 contract when it partnered with Kentucky for new bridges across the Ohio River. Barney Allison and John Smolen* explain the groundbreaking availability payment deal. Earlier this year, traffic began rolling over the new tolled Lewis and Clark Bridge spanning the Ohio River from northern Kentucky to southern Indiana. The cable-stayed bridge is part of the award-winning Ohio Bridges Project to untangle traffic within the greater metropolitan area of Louisville, Kent
  • Innovative Ohio River Bridge crossing
    March 31, 2016
    Work is underway on an innovative new bridge link over the Ohio River in the US.
  • Mountain View Partners to start on Calgary’s Southwest Ring Road
    July 19, 2016
    Preliminary utilities work is set to begin in September on the last section a ring road around the Canadian city of Calgary. The Calgary Herald newspaper quoted the Alberta provincial infrastructure and transportation minister Brian Mason saying that the project is on schedule. He said “everything is going as planned … It’s important that we keep on top of this and it’s important that we keep it moving forward and so far we’re doing just that.” The public-private-partnership project for the southwest
  • Cleveland Bridge is all decked out on the England’s A14 scheme
    June 4, 2019
    As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,