Skip to main content

Mersey Gateway: Consortia Talks

The competitive dialogue phase of the Mersey Gateway Project has begun. The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months. The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013. The value of the construction phase of the project, including land, is estimated at US$961milli
April 4, 2012 Read time: 3 mins
RSSThe competitive dialogue phase of the Mersey Gateway Project has begun.

The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months.

The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013.

The value of the construction phase of the project, including land, is estimated at US$961million.

Councillor Rob Polhill, Leader of Halton Borough Council, said: “The rest of this year will be critical in shaping the final detail of the bidders’ proposals, and we will be working closely with each bidding group to ensure that we are able to maintain quality on this project whilst continuing to deliver value for money for the public purse.”

Steve Nicholson, Mersey Gateway Project (MGP) director, said: “The quality of the initial submissions was excellent, and I am looking forward to working with each of the bidding groups to enable them to pull together their detailed proposals.”

Last month Halton Borough Council announced the identities of the three shortlisted bidders. They are:

1146 Balfour Beatty, 979 Bouygues Travaux Publics, 2376 EGIS Projects consortium, comprising equity members Balfour Beatty plc, Bouygues Travaux Publics and Egis Projects.

Merseylink consortium, comprising equity members 2378 Macquarie Capital Group Limited, 2516 Bilfinger and Berger Project Investments Limited, Vialia Sociedad Gestora de Concesiones de Infraestructuras S.L. and 1340 FCC Construcción S.A.

MGL consortium, comprising equity members 3932 Galliford Try Investments Limited, 981 Hochtief PPP Solutions GmbH and 3933 Iridium Concesiones de Infraestructuras S.A.

The centrepiece of the MGP is a new six-lane toll bridge over the Mersey between the towns of Runcorn and Widnes.

In addition to speeding up journey times and improving journey reliability in the region, it is intended to act as a catalyst for investment and bring benefits over four times greater than the investment cost.

The benefits are predicted to include the creation of an estimated 4,640 new jobs through direct employment, regeneration activity and inward investment, and the generation of a conservative estimate of $99million a year in Gross Value Added from the new jobs by 2030.

The existing Silver Jubilee Bridge will also be tolled as part of the project.

It is anticipated that construction work will start within two years, and that the new bridge will take around three years to complete.

As well as the income from tolls, the 5432 Department for Transport will provide $138million in capital grant towards land and remediation and up to $23.3million per year in long-term revenue support for 26.5 years from opening to fund the scheme.

For more information on companies in this article

Related Content

  • Amsterdam tunnel widening project
    February 23, 2017
    In Amsterdam widening work is now underway on the A10 motorway project close to Zuidas. The project is expected to take 10 years in all to complete and is being carried out in a bid to cut congestion at peak periods. Costing €990 million, the work is being carried out by a consortium that comprises local firm Heijmans, US company Fluor and the German contractor Hochtief. The project was awarded to the consortium by the Dutch infrastructure board Rijkswatersaat, the local council of Amsterdam, the rail servi
  • Land acquisition delays the start of Bratislava's orbital road
    September 25, 2017
    Land acquisition issues have stalled the start of construction of Bratislava’s orbital road by up to eight months. Work could begin this autumn, according to a report by the Slovak Spectator, because the government is working on laws that would allow construction before all land is acquired.
  • Veenix wins Dutch A9 widening work
    September 13, 2019
    The consortium Veenix, which includes Macquarie Capital, FCC, Count & Cooper and Siemens, will widen a 1.3km section of the A9 motorway in the Netherlands. The losing consortium has not appealed against the open tender decision for the contract which Rijkswaterstaat – the Dutch infrastructure and water authority – says will be around €808 million. There are no Dutch companies in the Veenix consortium.
  • New road tunnels are planned for Switzerland
    July 24, 2012
    Two key tunnel projects are being planned in Switzerland at present, for projects at Jura and Gothard. The Swiss Federal Department for Infrastructure Uvek now intends to build a third tunnel at Jura Mountain by 2022. This will be the third link for Motorway 2 and will be completed before renovation work is carried out on the two existing tunnels. The new link will provide four lanes and ensure traffic flow continues while the existing links are improved. The construction of the third tunnel is expected to