Increasing costs of highways project delays

Costs are climbing for Catalonia’s Eix de la Conreria highway project in Spain. The B-500 project is now expected to cost €400 million, a jump of €30 million from the previous estimate made just six months ago. The new link will connect Barcelona with Baix Maresme and Valles and the start of work on the project is also now expected to be delayed until 2012. The project requires the construction of four lanes with two running in either direction and is at present in the design and environmental assessment s
May 15, 2012 Read time: 1 min
Costs are climbing for Catalonia’s Eix de la Conreria highway project in Spain.

The B-500 project is now expected to cost €400 million, a jump of €30 million from the previous estimate made just six months ago. The new link will connect Barcelona with Baix Maresme and Valles and the start of work on the project is also now expected to be delayed until 2012. The project requires the construction of four lanes with two running in either direction and is at present in the design and environmental assessment stages.

The new link will be run and managed by concession company 1550 Tabasa, which currently operates the Vallvidriera tunnels.

Tabasa will finance much of the work through its own sources although the link will be tolled which will help provide cash flow once it is constructed.

Related Content

  • Chile highway construction works planned
    May 12, 2017
    The Chilean Government is planning a series of major highway projects with the Ministry of Public Works (MOP) managing the works. The plans call for 14 concessions worth a total of US$3.74 billion to be awarded by January 2018. The second stage of Americo Vespucio Oriente highway (AVO 2) is costing $800 million and is a priority project. This has been delayed already and opening of the route is now expected for 2022. Five regional highways are also opening for tender, including the Ruta G-21 road link, whic
  • Russia to commission new Moscow-St Petersburg highway by 2020
    June 20, 2017
    Final delivery of the final stretch for Russia’s key highway project looks set to be delayed – Eugene Gerden writes. I now looks as if Russia’s most ambitious project in the field of road building in recent years, the building of a new high-speed road link between Moscow and St Petersburg, the country’s largest cities, will not be complete in time. The project was set up by the Russian government and several private investors. According to initial state plans, building of the new road should have been compl
  • Egypt’s road programme is now restarting
    February 20, 2014
    Egypt is developing its road network – local reporting and images by Egypt correspondent Mohammed Elsayed Tantawy. Egypt is now gearing up its road construction activity, with a view to reducing congestion and improving traffic flow. The country’s main highway connecting capital Cairo with the port city of Alexandria has already seen a major widening programme, but other important routes are also now being upgraded and improved. The road development programme started in earnest some years ago but was delaye
  • Delays on Slovakian projects
    July 9, 2012
    Work on several new highways being built in Slovakia as public-private partnerships (PPPs) will be delayed by six to 12 months. This means that the first sections of the Martin-Presov link will not open before 2011. The last section is expected to be completed in either late 2012 or early 2013.