German court decides for Fehmarnbelt

Danish state-owned company Femern is responsible for the 18km road-rail tunnel.
By David Arminas November 18, 2020 Read time: 1 min
Work continues in June on a breakwater for the harbour in Rødbyhavn where sections of the tunnel will be constructed and floated out for placement (photo copyright Femern/Nils Lund Pedersen)

Germany’s federal administrative court has decided that the planned Fehmarnbelt Tunnel between the Danish island of Lolland and the German island of Fehmarn can proceed.

The case to delay construction began at the end of September. Six of the nine complaints were recently dismissed unconditionally while three complaints were settled out of court, according to the German newspaper Suddeutsche Zeitung.

The Danish state-owned company Femern is financing, building and will operate the approximately 18km road and rail tunnel under the Baltic Sea at a cost around €7.5 billion to construct. The tunnel, expected to open in 2029, should reduce the passenger train time from Hamburg in northern Germany to the Danish capital Copenhagen by around two hours, making the journey around two and a half hours.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with Femern. The joint venture has also worked on other landmark infrastructure projects, including the Øresund Tunnel in Denmark, the City Tunnel in Malmö, Sweden, the Medway Tunnel in England, as well as underground rail systems in Amsterdam and Copenhagen.

COWI is carrying out the detailed design of the tunnel (north tunnel section, south tunnel section, and ramps and portals). Meanwhile, SWECO is handling the design for the dredging and reclamation work.

For more information on companies in this article

Related Content

  • Plans in hand for Denmark-Germany tunnel link
    January 25, 2013
    The tender pre-selection process is underway for the new tunnel link that will connect Denmark with Germany. Danish state-owned company Femern said that interest is strong in the project to build the tunnel, which will run under the Baltic Sea. So far nine consortia comprising 24 companies in all are taking part in the tender pre-selection process. The Fehmarn Belt Fixed Link will feature an immersed tunnel and its construction is expected to cost some €5.5 billion. There are four main contracts including d
  • Immersed tube Fehmarnbelt Tunnel approved
    February 21, 2012
    The Danish government has given its approval for the construction of the 18km immersed tube Fehmarnbelt Tunnel, which will connect the country with Germany.
  • German government to adhere to Fehmarn Belt tunnel plans
    April 30, 2015
    Germany is to adhere to plans for a tunnel between Fehmarn, Germany, and Lolland, Denmark despite criticism over the cost and a delayed schedule. Denmark alone is likely to foot the €7.4 billion bill for the prestigious Fehmarn Belt Fixed Link immersed tunnel while Germany will pay for only access roads and other connections on its territory. Angela Merkel, Chancellor of Germany, said her government and transport authorities will respond to more than 3,000 objections over the construction of the tunne
  • Denmark eyes Little Belt Fixed Link
    November 8, 2023
    The directorate is concerned that the so-called New Little Bridge, which opened in 1970, will suffer severe traffic congestion from 2030 onwards.