Funding problems for major Polish highway project

The long tale of woe concerning Poland’s troubled A2 highway project looks set to continue with the latest developments in the case. The Chinese contractor China Overseas Engineering Group Co (Covec) is appealing against a decision made by the Polish national road authority GDDKiA. The Polish authorities cancelled the contract that COVEC had previously been awarded to build a section of the A2 highway between Warsaw and Lodz.
May 9, 2012 Read time: 3 mins
The long tale of woe concerning Poland’s troubled A2 highway project looks set to continue with the latest developments in the case.

The Chinese contractor China Overseas Engineering Group Co (2487 COVEC) is appealing against a decision made by the Polish national road authority 1361 GDDKiA. The Polish authorities cancelled the contract that COVEC had previously been awarded to build a section of the A2 highway between Warsaw and Lodz.

The highway is an important one as it will link the Polish and German capitals Warsaw and Berlin respectively. Covec’s deal was a landmark decision, the first time a Chinese firm had won a major construction contract in Europe. The firm won the tender process for the 50km highway stretch with a low bid that caused some controversy as other bidders complained about being undercut. The problems started soon after Covec commenced work, with materials prices spiralling and causing major problems for the Chinese firms. As delays with the work mounted and complaints from local sub-contractors over non-payment by the main contractor grew, Covec was forced to withdraw from the project in May. Covec has now complained that it has been unfairly treated by the Polish authorities and at present, the case looks likely to end up in the Polish courts.

Work on two sections of Poland’s A2 highway will now be constructed by two consortia. The 3281 Eurovia-3544 Warbud consortium will build the 29km A section, which will cost €246.63 million. The 20km C section will be built by the Boegl & Krysl-DSS consortium and will cost €188.54 million. The contracts were awarded by the GDDKiA.

Poland’s Ministry of Infrastructure is in talks with the 1166 European Bank for Reconstruction and Development (EBRD) and the 1054 European Investment Bank (EIB) as well as other financial institutions. The aim of the talks is to find solutions to highway financing issues, without increasing public debt. Before the end of 2011, two major highway tenders will be announced in Poland. One of these will be for work to the A2 highway between capital Warsaw and Poland's eastern border. The other will be for a 140km section of the A1 highway between Tuszyn and Pyrzowice. Experts say that the A1 project could be carried out under a public-private partnership (PPP) because the highway will carry heavy traffic volumes. A number of private partners have put themselves forward for this PPP proposal including 2296 Skanska and 7167 Meridiam.

Related Content

  • Delays on Slovakian projects
    July 9, 2012
    Work on several new highways being built in Slovakia as public-private partnerships (PPPs) will be delayed by six to 12 months. This means that the first sections of the Martin-Presov link will not open before 2011. The last section is expected to be completed in either late 2012 or early 2013.
  • Delayed ring road due for completion
    May 15, 2012
    In Romania, modernisation of capital Bucharest’s ring road is now due for completion in 2012. The delay has been caused by a lack of funds. Upgrading of the sections between DN7 and DN1A and DN1A (Mogosoaia)and DN1 (Otopeni) started in 2007 and some 51km have been improved so far. The total length of the ring road will be 71km when it is complete. Tenders still have to be launched for two more sections of the ring road, the 11km DN2/A2 stretch and the 8.6km A1/DN7 section. Financing for these last section
  • FIEC criticises contract awards and procurement practices
    January 20, 2014
    Europe’s contractors’ association, the FIEC, has criticised the EU’s new public procurement package, describing it as a missed opportunity. “The EU institutions did not seize the opportunity to solve one of the most severe shortcomings of the existing public procurement directives,” said Ulrich Paetzold, FIEC director general. “I mean by that the identification and treatment of abnormally low tenders, which is a real curse in the construction sector.” Today’s adoption by the European Parliament of the thre
  • Vehicle emissions strategy
    July 3, 2012
    Environmental questions are facing the construction of the Martin-Presov highway in Slovakia. The European Investment Bank (EIB) and European Bank for Reconstruction and Development (EBRD) are waiting to receive approval to fund construction of the highway in Slovakia from the European Commission (EC). However the EC is not giving its approval for the loans at present until the Slovak Government provides answers as to why the route goes through a national park. Although the Slovakian Transport Ministry is k