Delayed ring road due for completion

In Romania, modernisation of capital Bucharest’s ring road is now due for completion in 2012. The delay has been caused by a lack of funds. Upgrading of the sections between DN7 and DN1A and DN1A (Mogosoaia)and DN1 (Otopeni) started in 2007 and some 51km have been improved so far. The total length of the ring road will be 71km when it is complete. Tenders still have to be launched for two more sections of the ring road, the 11km DN2/A2 stretch and the 8.6km A1/DN7 section. Financing for these last section
May 15, 2012 Read time: 2 mins
In Romania, modernisation of capital Bucharest’s ring road is now due for completion in 2012. The delay has been caused by a lack of funds.

Upgrading of the sections between DN7 and DN1A and DN1A (Mogosoaia)and DN1 (Otopeni) started in 2007 and some 51km have been improved so far. The total length of the ring road will be 71km when it is complete.

Tenders still have to be launched for two more sections of the ring road, the 11km DN2/A2 stretch and the 8.6km A1/DN7 section. Financing for these last sections will be provided in part by a €50 million loan from the 1054 European Investment Bank, which is expected to cover around 50% of the costs.

Meanwhile the 1207 SEARCH Corporation is now working on a feasibility study for the construction of Targu Mures-Ditrau highway. Search was contracted by the National Highways and Roads Company.

For more information on companies in this article

Related Content

  • Ring road upgrade for Bucharest
    May 4, 2012
    Plans are in hand in Romania for the upgrades to the Bucharest ring road. This work is due to be completed by 2014, according to the country’s Transport Ministry. Reconstruction and modernisation of the Chitila-Voluntari segment of the ring road was completed in 2010 and the modernisation of another two segments were completed in 2011. Also, the upgrading of two further segments will be finished by mid 2013. The investment in the five segments of the ring road is expected to reach €100.17 mill
  • Bids in for Bucharest Ring Motorway segment
    April 3, 2024
    The 101km-long motorway - also called the Bucharest Belt Motorway and the A0 Motorway -will be an outer ring highway to the existing inner Bucharest Ring Road around the Romanian capital city.
  • Bids in for next Bucharest A0 orbital work
    August 10, 2021
    The A0 orbital motorway will run about 100km around the Romanian capital.
  • Romanian road issues
    March 5, 2012
    Political controversy is looming with the revelation that Romania's National Road Company (CNADNR) has spent some €1.5 billion on upgrading 2,800 km of roads since 2004.