Skip to main content

Funding doubts over major highway project

Slovakia’s troubled D1 highway project continues to be a topic of controversy in the country, with doubts over whether there are sufficient funds to pay for the completion of the route. A political debate focuses on whether the Transport Ministry should have extended the deadline for the agreement of the financial package for the first tranche of contracts for the highway. The Slovenske Dialnice consortium recently met with the Transport Ministry over the decision not to continue with the PPP project to c
May 15, 2012 Read time: 2 mins
Slovakia’s troubled D1 highway project continues to be a topic of controversy in the country, with doubts over whether there are sufficient funds to pay for the completion of the route.

A political debate focuses on whether the Transport Ministry should have extended the deadline for the agreement of the financial package for the first tranche of contracts for the
highway.

The Slovenske Dialnice consortium recently met with the Transport Ministry over the decision not to continue with the PPP project to construct five stages totalling 75km of the highway. The consortium has put in €32 million worth of preliminary work into the highway so far.

The consortium says that the documentation for the highway stages worked on so far will be handed over to Slovakia’s government once the contract is revoked and compensation has been paid for costs associated with the project.

Meanwhile, a 5km section of the D1 highway near Levoca, which cost €72 million to build, and was only opened in June this year, is already said to need repairs. Speed restrictions have been imposed and repairs are planned to start later
this year.

Construction of other sections near Ruzomberok and Levoca is expected to start in summer 2011.

Related Content

  • Funding problems for major Polish highway project
    May 9, 2012
    The long tale of woe concerning Poland’s troubled A2 highway project looks set to continue with the latest developments in the case. The Chinese contractor China Overseas Engineering Group Co (Covec) is appealing against a decision made by the Polish national road authority GDDKiA. The Polish authorities cancelled the contract that COVEC had previously been awarded to build a section of the A2 highway between Warsaw and Lodz.
  • Poland's ambitious highway construction plans
    July 10, 2012
    The European football championships are among a number of things pushing Poland's ambitious highway building programme. Patrick Smith reports. Poland is planning to spend a colossal €4.57 billion on road projects in 2009, a 35% increase over the previous year. T
  • Slovakia tunnel sections underway but some delays
    January 23, 2018
    The route for new tunnel links for Slovakia’s D1 highway has been agreed. New tunnels now look set to be built on the 13.5km stretch between Turany and Hubova section of the D1 highway. This plan calls for the construction of the Korbelka and Havran tunnels at an estimated cost of €900 million. Building these two links would bypass the Lower Fatra mountain range, with the Korbelka Tunnel measuring 5.9km and the Havran Tunnel measuring 2.9km long. The Slovak Environment Ministry rejected an appeal against th
  • Slovakia, Salini Impreglio to part ways over D1-Višňové tunnel work
    March 11, 2019
    Slovakia and the Italian-Slovak consortium of Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel. The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed