Chilean bridge project to Chiloe Island delayed

Delays to the project to construct Chile’s Chacao Bridge mean that an additional two years may be required for the work. The work is now being carried out solely by a consortium, Consorcio Puente Chacao, headed by the South Korean contractor Hyundai.
October 31, 2018 Read time: 2 mins

Delays to the project to construct Chile’s Chacao Bridge mean that an additional two years may be required for the work. The work is now being carried out solely by a consortium, Consorcio Puente Chacao, headed by the South Korean contractor 236 Hyundai. The consortium asked for an extra US$200 million to carry out the project, in addition to extending the work by two years. The bridge was originally planned to be complete by 2020 but the various delays so far mean that it will not now be ready for traffic until 2023. The extra costs mean that the final bill for the project could be $900 million. 

A suspension bridge design was selected  for the link as it was thought to be best able to cope with the extremes of weather, as well as the massive earthquakes that can occur in the area. At 2.75km long, this will be South America’s longest suspension bridge once complete, with main spans of 1,055 and 1,155m. According to Hyundai, progress is being achieved on the project and the design for the south pillar is now complete.

Once the bridge is complete it will help to redevelop the economy of Chiloe Island. At present the inhabitants rely on a ferry service however the new bridge will speed transport and reduce journey times, boosting the economy and also helping to develop tourism. 

The bridge has been discussed for some years. An earlier plan for the project was cancelled over concerns about its costs. However the current project was commissioned as the suspension bridge configuration offered considerable cost benefits over the previous design, while delivering the expected connectivity to the island.
 

For more information on companies in this article

Related Content

  • Hyundai E&C is working on Turkey’s new third Bosporus Bridge
    July 10, 2013
    Hyundai Engineering & Construction (Hyundai E&C) is to head a consortium building the lateral towers, aprons and suspension cables for the new Bosporus crossing in Turkey. Hyundai E&C will work in a consortium with its partner SK Engineering & Construction on the US$697 million project to construct the 2.16km Third Bosporus Bridge. This suspension bridge will feature eight lanes for motor vehicle traffic as well as two rail lines. With a width of 59m it will be the widest bridge in the world that carries a
  • Latin America invests in infrastructure growth
    February 15, 2012
    Travelling in one of the world's most diverse regions is not always easy, but spectacular engineering feats will make life easier as Patrick Smith reports. Five years ago a report from the World Bank noted that infrastructure in most of Latin America and the Caribbean (LAC) had improved over the previous ten years.
  • Denmark set to appoint preferred bidder for Fehmarnbelt link
    March 14, 2016
    The Danish political parties behind the Fehmarnbelt link have mandated Femern A/S to appoint preferred bidders for the main tunnel work in order to enter into conditional contracts no later than mid-May. Femern A/S is the Danish government-owned company managing the Fehmarn Belt immersed tunnel project between Denmark and Germany. The project was approved by the Danish parliament in April last year. It is supposed to be built, owned - apart from the German land works - and operated by Femern A/S, a su
  • Chilean deal
    February 6, 2012
    Skanska is preferred bidder to develop the Antofagasta Toll Road in Chile under a PPP model. The firm has beaten tough competition for this project and says it will not require government subsidies for the work, which is due to commence in 2011.