Auckland’s causeway project

When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.
April 4, 2014 Read time: 3 mins
Part of the 4.8km Causeway Upgrade Project on Auckland's North-western motorway which runs through a marine reserve, looking east towards the city - Photography by Greg Kempthorne
When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.

More than 10,000 wick drains have already been installed to accelerate consolidation of up to 15m of alluvial marine mud as part of the NZ Transport Agency’s 4.8km, US$183.3 million (NZ$220 million) Causeway Upgrade Project. “Intensive ground reclamation like this is an important part of the project’s work to upgrade and improve this section of the motorway. We are mindful to protect the marine reserve environment where we are working, installing new bird roosts for species which inhabit the area, and silt fences,” said the Transport Agency’s highways manager, Tommy Parker. 

A 2-3M-deep drainage blanket using more than 26,000 truckloads of 19-25mm recycled aggregate has been spread on top of the wick drains. When the settlement has stabilised, construction of new motorway lanes will start on top of it.

The Causeway Alliance – the NZ Transport Agency, AECOM, Coffey, Fulton Hogan, Leighton Contractors and Sinclair Knight Merz – is completing the upgrade.
 
The project is one of five underway or planned to finish the 47km-long Western Ring Route along the South-western, North-western and Upper Harbour motorways, which is identified by the Government as one of its Roads of National Significance to support New Zealand’s economic growth.

The project is the first in New Zealand to adopt temporary orange marking tape to improve lane definition and enhance driver safety. Maintaining traffic flow of almost 100,000 vehicles/day while upgrading this section of the state highway network is a key challenge and driver cooperation is essential.

Mr Parker said that for the first time, Auckland will have direct motorway access between the central business district and the airport, and the Western Ring Route will also better connect people and freight with the city’s rapidly growing areas in the north-west and south-west. 

 “It’s a key part of a massive investment in infrastructure needed to meet the demands of rapid economic and population growth underway in the top half of the North Island,” he said. 

More detailed information on this project will be included in a feature in the April issue of World Highways.

Related Content

  • BarrierGuard’s successful New Zealand highway installation
    March 10, 2014
    Highway construction in the vast and varied Australasian landscape can be fraught with difficulties. Distance, extreme weather conditions and topographical challenges can all play a part in creating significant obstacles for design engineers. BarrierGuard 800, a state-of-the-art lightweight steel road safety barrier, is said to be proving invaluable in two ongoing projects setting new benchmarks for their respective regions. The US$895.7 million (AUS$1 billion) Gateway WA Perth Airport and Freight Acces
  • Building New zealand's landmark tunnel
    February 15, 2012
    A landmark tunnelling project is commencing in New Zealand - Kristina Smith reports. New Zealand is preparing to embark on its biggest transport project ever. In August it announced that it had selected its preferred bidder for the NZ$1.4 billion Waterview Connection in Auckland, 5km of new motorway connecting highways to the North and South of the city.
  • Auckland’s future strategic transport requirements
    July 5, 2012
    The Auckland Harbour Bridge is at the stage that it cannot cope with much more traffic, yet the population of the Auckland region continues to grow at a steady rate. Coupled with that, the bridge is a key link in the most important transport corridor in the country, State Highway One. Without it, the country would struggle to function. Not only home to New Zealand's largest city and one third of its population, Auckland's port is one of the country's largest. Some 140m north of the city is Marsden Point, th
  • State-of-the art road tunnels in construction and use of ITS
    April 25, 2013
    A wealth of major road tunnel construction projects and significant cant ITS installations within existing key road tunnels have been recently completed or will soon be underway. Guy Woodford examines some of them. A state-of-the art Tunnel Boring Machine (TBM) - the 10th largest ever to be built worldwide will be put to work later this year on New Zealand Transport Agency’s landmark Waterview Connection project in Auckland. The giant Herrenknecht-manufactured machine will be used to construct the twin 2.5