Auckland’s causeway project

When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.
April 4, 2014 Read time: 3 mins
Part of the 4.8km Causeway Upgrade Project on Auckland's North-western motorway which runs through a marine reserve, looking east towards the city - Photography by Greg Kempthorne
When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.

More than 10,000 wick drains have already been installed to accelerate consolidation of up to 15m of alluvial marine mud as part of the NZ Transport Agency’s 4.8km, US$183.3 million (NZ$220 million) Causeway Upgrade Project. “Intensive ground reclamation like this is an important part of the project’s work to upgrade and improve this section of the motorway. We are mindful to protect the marine reserve environment where we are working, installing new bird roosts for species which inhabit the area, and silt fences,” said the Transport Agency’s highways manager, Tommy Parker. 

A 2-3M-deep drainage blanket using more than 26,000 truckloads of 19-25mm recycled aggregate has been spread on top of the wick drains. When the settlement has stabilised, construction of new motorway lanes will start on top of it.

The Causeway Alliance – the NZ Transport Agency, AECOM, Coffey, Fulton Hogan, Leighton Contractors and Sinclair Knight Merz – is completing the upgrade.
 
The project is one of five underway or planned to finish the 47km-long Western Ring Route along the South-western, North-western and Upper Harbour motorways, which is identified by the Government as one of its Roads of National Significance to support New Zealand’s economic growth.

The project is the first in New Zealand to adopt temporary orange marking tape to improve lane definition and enhance driver safety. Maintaining traffic flow of almost 100,000 vehicles/day while upgrading this section of the state highway network is a key challenge and driver cooperation is essential.

Mr Parker said that for the first time, Auckland will have direct motorway access between the central business district and the airport, and the Western Ring Route will also better connect people and freight with the city’s rapidly growing areas in the north-west and south-west. 

 “It’s a key part of a massive investment in infrastructure needed to meet the demands of rapid economic and population growth underway in the top half of the North Island,” he said. 

More detailed information on this project will be included in a feature in the April issue of World Highways.

Related Content

  • Work commencing on key New Zealand tunnel link
    August 3, 2012
    New Zealand prime minister John Key led an official ground-breaking ceremony this week to allow the start of excavation work for two new 2.4km-long motorway tunnels beneath suburban Auckland. The Waterview Connection project is on schedule to begin its main construction phase next year, and the prime minister was on hand to turn the first soil for a 30m-deep trench which is needed to allow access for the tunnels’ southern approach trench in the west Auckland suburb of Owairaka.
  • New Zealand lobbyists want tunnel from Panmure to Auckland
    May 13, 2016
    Lobby group New Zealand Council for Infrastructure Development has released a report assessing Auckland's congestion problem which costs the city about US$1.02 billion a year. The city’s increasing car gridlock will grind the economy to a halt, said Stephen Selwood, the group’s chief executive. However, part of the solution, according to the report, could be a major 11km road tunnel from the Panmure district to Auckland’s central business district. Selwood criticised Auckland city’s transport policy p
  • New Zealand's transport plans
    February 8, 2012
    New Zealand's Government is now setting budgets for transport improvements. In Auckland transport projects look set to commence following a design agreement worth US$10.52 million. This will be for the $937 million eastern suburban transport projects package.
  • New Zealand announces massive infrastructure development programme
    January 30, 2020
    New Zealand’s massive infrastructure development programme has a key focus on transport improvements.