Zhejiang Jiashao Bridge Investment & Development Co

Located in Zhejiang Province of China, Jiashao Bridge spans the Qiantang River and connects the cities of Jiaxing and Shaoxing. The total length of the bridge project is 10.14km and carries an eight-lane expressway The Qiantang River suffers from a high flow rate of up to 7.5m/s. As the tidal range is around 7-9m, the water depth is less than 2m in time of low level tide, so ships can only move at high tide and large scale ship-lifting equipment cannot be used downstream of Jiashao Bridge. However, to
April 6, 2017 Read time: 3 mins
The high flow rate and tidal range of the Qiantang River is a challenge to vessels, as well as to the construction of the new bridge
RSSLocated in Zhejiang Province of China, Jiashao Bridge spans the Qiantang River and connects the cities of Jiaxing and Shaoxing. The total length of the bridge project is 10.14km and carries an eight-lane expressway

The Qiantang River suffers from a high flow rate of up to 7.5m/s. As the tidal range is around 7-9m, the water depth is less than 2m in time of low level tide, so ships can only move at high tide and large scale ship-lifting equipment cannot be used downstream of Jiashao Bridge.

However, to protect against the Qiantang tidal bore and reduce the construction risks under the difficult conditions, an innovative structure design was adopted for this bridge project. For the main bridge design, a six-pylon cable-stayed bridge with five 428m-long main spans is adopted. Single-pylon structure, with the top of pile caps located under the riverbed surface is used to control the water blocking rate of the bridge structure. The superstructure of the main bridge is separated by four-plane stud welding streamlined flat steel box girders. The total steel girder width reaches 55.6m.

To increase the vertical stiffness of the main girder effectively and control the temperature deformation of the whole 2680m-long main girder, an innovative double-support and hinge (DSH) system was adopted.

With the DSH system, there are two vertical supports set at both sides of the pylon for the steel box girder at the pylon bracket area, and four two-way sliding bearings for one pylon. Using the DSH system, the scale of pylons and foundations were reduced, and US$139.8 million was saved compared to traditional designs without hinges.

In order to enhance the integral stability of the structure with tall and flexible single-pile-column foundations, I-shape transversal beams were set between the separated decks. The single-pile-column substructure had a small water-blocking area, which had a small influence on hydrology. And with no pile cap, it avoided the risk of cofferdam construction from the tidal bore.

The completed Jiashao Bridge now features an elegant and integral structural design. The application of the DSH system and hinge-related technologies, including design, manufacturing, erection, monitoring, and maintenance promotes the theoretical and technical development of multi-pylon cable-stayed bridges and contributes to the promotion of multi-pylon cable-stayed bridges worldwide.

Wang Zhangxuan, vice general manager of Jiashao Bridge Investment & Development Co said, “On behalf of Zhejiang Jiashao Bridge Investment & Development Co of China, I am very grateful that the 3918 IRF Washington has awarded the 2016 Design GRAA to the Jiashao Bridge project.

It was a great challenge for the designers, CCCC Highway Consultants Co, to account for the Qiantang River tide and incorporate appropriate technical and material innovations for design and construction. I welcome bridge specialists from around the world to come to China and visit the project; we are happy to exchange and share experiences and concepts with each other.”

For more information on companies in this article

Related Content

  • The 2016 Global Road Achievement Awards have been announced
    January 27, 2017
    The International Road Federation recently announced the winners of the 2016 IRF Global Road Achievement Awards at a ceremony held during the 2nd IRF Asia Regional Congress & Exhibition. This year, the IRF honours 12 projects from around the world, each leading the way in innovation across major road & highway disciplines. The selection was made by an international panel of senior road development specialists.
  • Kronprinsesse Marys Bro bridges Roskilde Fjord
    January 10, 2019
    A BESIX joint venture is giving the royal treatment to the new Kronprinsesse Marys Bro across Roskilde Fjord, writes David Arminas It was announced in September 2016 that Belgian group BESIX, in a joint venture (RBAI) with Italian firm Rizzani de Eccher and Spanish company Acciona Infraestructuras, had been chosen for the €133 million project. The award, by client Vejdirektoratet (Danish Road Directorate), marked the entry of BESIX into the Scandinavian market. Vejdirektoratet praised the winning bid as
  • The Mersey Gateway bridge project continues on schedule
    October 18, 2016
    Work continues on the 2.3km Mersey Gateway signature bridge project close to Liverpool in the UK. David Arminas reports on some of the construction highlights. Under construction is a cable-stayed structure with three towers that will span the Mersey River’s expansive mud flats between the towns of Runcorn and Widnes near Liverpool. Including the approach viaducts on each side, it will be 2.3km long with a river span of 1km. The main bridge deck will be reinforced concrete. The 80m-high central tower will b
  • Emergent markets key for formwork sector growth
    May 21, 2014
    Central and south-east Europe are hotbeds for new highway infrastructure projects utilising cutting-edge formwork solutions, while a number of leading formwork manufacturers are also looking at emergent markets for growth. Guy Woodford reports Travelling between Hungary’s capital Budapest and Southern Dalmatia now takes less time thanks to the Pan-European Corridor Vc – European route 73. Numerous tunnels and bridges are erected along the 397km stretch of the European route 73 through Bosnia owing to the