Realigning Kenyan bypass to avoid quagmire and ease congestion

Japanese consultants are planning to realign a Kenyan bypass, as Shem Oirere reports. Japanese consultants are resolving an engineering quagmire involving a 17.5km bypass in Kenya's Coast region. The new design realigning the bypass is underway by Japanese International Cooperation Agency (JICA) consultants. The road is an alternative link from the hinterland to the south coast and to the proposed Dongo Kundu Port. The 23m-wide bypass would also serve to reduce traffic congestion across the Likoni Channel.
March 22, 2012 Read time: 4 mins
Realignment of a planned 17.5km bypass in Kenya will help overcome the sloppy stretches and sections under mangrove

Japanese consultants are planning to realign a Kenyan bypass, as Shem Oirere reports

Japanese consultants are resolving an engineering quagmire involving a 17.5km bypass in Kenya's Coast region.

The new design realigning the bypass is underway by Japanese International Cooperation Agency (JICA) consultants. The road is an alternative link from the hinterland to the south coast and to the proposed Dongo Kundu Port. The 23m-wide bypass would also serve to reduce traffic congestion across the Likoni Channel through to the ferry, according to the 2639 Kenya National Highways Authority (KeNHA), a state agency mandated to develop highways in the country.

The bypass is part of the 2332 World Bank-funded Northern Corridor Transport Improvement Project, an infrastructure improvement project funded by the International Development Agency (IDA) of the World Bank Group. The corridor runs from Mombasa to the Great lakes region, and is an important road link for trade and communication in the country and in the region. It seeks to link Kenya with Tanzania and Sudan.

It is expected that the bypass, in the pipeline for over 40 years, will be developed into a coastal highway in East Africa linking Tanzania’s capital Dar es Salaam to Kenya’s tourist-famous Malindi town.

The realignment of the US$45 million bypass will help overcome the sloppy stretches and sections under mangrove, with the consultants also seeking to reduce the number of people to be displaced to pave the way for the project. Initially a total of 600 land owners were to be displaced but now JICA consultants are working at leaving out an estimated 253 households under the realigned project.

“The original project design is being reviewed by the JICA consultant team so as to ensure that fewer people are affected, natural conditions are preserved, better alignments and road reserves are secured for the necessary developments, and expansion of the road at present and in the future,” KeNHA says in a briefing on the project.

The JICA consultant, Katahira and Engineers International, say the new bypass plan will not only mitigate the expected challenge posed by the mangroves and steep slopes for operations of loaded trucks, but will also reduce the number of affected people and cultural sites to be demolished by the construction.

“By avoiding crowded areas, we will reduce the construction costs,” Kioyoshi Mukai, one of the experts was recently quoted as saying.

Katahira’s executive director Soemu Oshita said: “We wanted the road to pass through less crowded areas so as to get enough space for future expansion.”

Another expert, Koyo Ogasawara said: “We will make sure that there are minimal effects on mangroves during the construction of the two big bridges across Mwache and Mteza creeks.”

According to the initial project plan, designed by infrastructure and business services group 2377 Mouchel Parkman/CAS, the bypass is to start at Miritini Township and pass overland to join road A14 from Likoni to Ukunda, with a large portion of the project consisting of a bridge connecting the island of Mombasa to mainland Kenya.

The project has two major components and will also involve the widening of the 2km road to the Moi International Airport in Mombasa.

Phase one of the bypass consists of the 17.5km road starting from Miritini, west of Moi International Airport, on the central south mainland, passing through the proposed Dongo Kundu Port on the south mainland and ending at Vumirirani on the A14 Coast Road.

Two viaduct bridges will be constructed: the 495m long Mwache at Mkupe, which will cross water; while of the 1,360m long Mteza at Dongo Kundu, 760m will be across mangrove and mud flats (600m across water).

Phase two of the project involves improvement of roads supplementing the bypass on the north mainland and Mombasa Island. The roads include Barack Obama (2.5km); Port Reitz (2.3km); Magongo (0.6km); Mombasa Western Relief (2.6km); and a 6km link road from the proposed new container terminal to the bypass. A four-lane bridge will also be constructed over the railway to connect to Lumumba Road.

When completed in three years, the two components of the project will help reduce congestion at the three links to Mombasa Island (Makupa Causeway, Nyali Bridge and Likoni Ferry), which on average carry 82,000 vehicles/day.

Permanent Secretary in the Ministry of Roads Michael Kamau, says the over-reliance on Likoni Ferry to connect to Mombasa Island is no longer feasible.

“Increased economic activity and population growth demand an uninterrupted flow of traffic and goods, and this can only be made possible by the Dongo Kundu bypass,” he said.

For more information on companies in this article

Related Content

  • Consultancy WSP|Parsons Brinckerhoff changing name
    January 11, 2017
    Leading consultant firm WSP|Parsons Brinckerhoff is changing its name to WSP in May 2017. The firm says that the name change reflects its recent growth to around 36,700 people globally with 7,100 based in the UK. The new name will cover more than 85 small and mid-sized to large companies that have previously been incorporated into the business. This includes Mouchel Consulting, which was acquired in October 2016, and will become WSP in July when it is fully integrated with the wider business. The name c
  • Balfour Beatty begins construction of €23.05mn Merseyside motorway link
    January 31, 2014
    Balfour Beatty this week began construction on a €23.05 million (£19 million) scheme to bypass two congested villages and link communities in Sefton along the west coast of Merseyside in Northwest England directly to the M57 and M58 motorways. The road will be 4.5km long and connect the A565 Southport Road to the motorway junction at Switch Island, avoiding the villages of Thornton and Netherton. The newly designated A5758 Broom’s Cross Road will relieve long-standing traffic issues in the area and provid
  • Kenya’s elevated highway gets a green light from the World Bank
    August 18, 2016
    The World Bank agreed to finance construction of Kenya’s first double deck highway, according to media reports. Construction is set to begin by the end of this year on the toll road to link Jomo Kenyatta International Airport and the Nairobi-Nakuru highway. Peter Mundinia the director-general of the Kenya National Highways Authority, explained that construction of the all-elevated dual carriageway will be in three phases. The first will begin with 6.5km running from the airport to Likoni Road and the
  • Nairobi revives city decongestion plan
    March 18, 2016
    Nairobi is looking to tackle its congestion problems - Shem Oirere writes. Authorities in Kenya’s capital Nairobi have revived plans to convert some of the streets in the city into one way roads to deal with chronic traffic congestion that consumes fuel worth millions of shillings and wastes several manhours in traffic jams. Nairobi County governor Dr Evans Kidero said the plan, which is to take effect by the end of December 2015, will affect Moi Avenue, Koinange Street, Tom Mboya Street, River Road and Kir