Realigning Kenyan bypass to avoid quagmire and ease congestion

Japanese consultants are planning to realign a Kenyan bypass, as Shem Oirere reports. Japanese consultants are resolving an engineering quagmire involving a 17.5km bypass in Kenya's Coast region. The new design realigning the bypass is underway by Japanese International Cooperation Agency (JICA) consultants. The road is an alternative link from the hinterland to the south coast and to the proposed Dongo Kundu Port. The 23m-wide bypass would also serve to reduce traffic congestion across the Likoni Channel.
March 22, 2012 Read time: 4 mins
Realignment of a planned 17.5km bypass in Kenya will help overcome the sloppy stretches and sections under mangrove

Japanese consultants are planning to realign a Kenyan bypass, as Shem Oirere reports

Japanese consultants are resolving an engineering quagmire involving a 17.5km bypass in Kenya's Coast region.

The new design realigning the bypass is underway by Japanese International Cooperation Agency (JICA) consultants. The road is an alternative link from the hinterland to the south coast and to the proposed Dongo Kundu Port. The 23m-wide bypass would also serve to reduce traffic congestion across the Likoni Channel through to the ferry, according to the 2639 Kenya National Highways Authority (KeNHA), a state agency mandated to develop highways in the country.

The bypass is part of the 2332 World Bank-funded Northern Corridor Transport Improvement Project, an infrastructure improvement project funded by the International Development Agency (IDA) of the World Bank Group. The corridor runs from Mombasa to the Great lakes region, and is an important road link for trade and communication in the country and in the region. It seeks to link Kenya with Tanzania and Sudan.

It is expected that the bypass, in the pipeline for over 40 years, will be developed into a coastal highway in East Africa linking Tanzania’s capital Dar es Salaam to Kenya’s tourist-famous Malindi town.

The realignment of the US$45 million bypass will help overcome the sloppy stretches and sections under mangrove, with the consultants also seeking to reduce the number of people to be displaced to pave the way for the project. Initially a total of 600 land owners were to be displaced but now JICA consultants are working at leaving out an estimated 253 households under the realigned project.

“The original project design is being reviewed by the JICA consultant team so as to ensure that fewer people are affected, natural conditions are preserved, better alignments and road reserves are secured for the necessary developments, and expansion of the road at present and in the future,” KeNHA says in a briefing on the project.

The JICA consultant, Katahira and Engineers International, say the new bypass plan will not only mitigate the expected challenge posed by the mangroves and steep slopes for operations of loaded trucks, but will also reduce the number of affected people and cultural sites to be demolished by the construction.

“By avoiding crowded areas, we will reduce the construction costs,” Kioyoshi Mukai, one of the experts was recently quoted as saying.

Katahira’s executive director Soemu Oshita said: “We wanted the road to pass through less crowded areas so as to get enough space for future expansion.”

Another expert, Koyo Ogasawara said: “We will make sure that there are minimal effects on mangroves during the construction of the two big bridges across Mwache and Mteza creeks.”

According to the initial project plan, designed by infrastructure and business services group 2377 Mouchel Parkman/CAS, the bypass is to start at Miritini Township and pass overland to join road A14 from Likoni to Ukunda, with a large portion of the project consisting of a bridge connecting the island of Mombasa to mainland Kenya.

The project has two major components and will also involve the widening of the 2km road to the Moi International Airport in Mombasa.

Phase one of the bypass consists of the 17.5km road starting from Miritini, west of Moi International Airport, on the central south mainland, passing through the proposed Dongo Kundu Port on the south mainland and ending at Vumirirani on the A14 Coast Road.

Two viaduct bridges will be constructed: the 495m long Mwache at Mkupe, which will cross water; while of the 1,360m long Mteza at Dongo Kundu, 760m will be across mangrove and mud flats (600m across water).

Phase two of the project involves improvement of roads supplementing the bypass on the north mainland and Mombasa Island. The roads include Barack Obama (2.5km); Port Reitz (2.3km); Magongo (0.6km); Mombasa Western Relief (2.6km); and a 6km link road from the proposed new container terminal to the bypass. A four-lane bridge will also be constructed over the railway to connect to Lumumba Road.

When completed in three years, the two components of the project will help reduce congestion at the three links to Mombasa Island (Makupa Causeway, Nyali Bridge and Likoni Ferry), which on average carry 82,000 vehicles/day.

Permanent Secretary in the Ministry of Roads Michael Kamau, says the over-reliance on Likoni Ferry to connect to Mombasa Island is no longer feasible.

“Increased economic activity and population growth demand an uninterrupted flow of traffic and goods, and this can only be made possible by the Dongo Kundu bypass,” he said.

For more information on companies in this article

Related Content

  • Indonesia’s Trans-Sumatra highway inches ahead
    March 11, 2015
    Indonesia will form a consortium of state enterprises to build all the 2,700km of the Trans-Sumatra toll highway, from Lampung to Aceh on the island of Sumatra. The finance department is also setting up special infrastructure banks to provide flexible loans for the state departments to fund the project, Indonesian media reported. Indonesia recently changed the law that had the state infrastructure company PT Hutama Karya as the only organisation allowed to build major projects. Other state enterprises can n
  • Road funding from Japan for Philippines
    November 11, 2019
    The Japan International Cooperation Agency (JICA) is providing the funding for a series of major infrastructure projects in the Philippines. In all eight road and bridge projects being built in the Philippines at present are being funded by the JICA. These are worth around US$1.2 billion. The projects include the Central Luzon Link Expressway, the Metro Manila Interchange, the Arterial Road Bypass, a programme of road upgrades across the nation, the Marawi road project, road improvements in Mindanao and th
  • Japanese funding for Philippines tunnel project
    January 30, 2017
    A new tunnel project in the Philippines is to be constructed with the help of Japanese funding. The project calls for the building of a new tunnel section connecting the centre of Davao City with its southern tip. Necessary funding for the work is being provided by the Japan International Cooperation Agency (JICA). The official development assistance (ODA) loan being provided by the JICA is worth US$232.74 million. The new Davao City bypass construction project in 2015 will be developed using Japanese exper
  • Transport development for Mindanao in Philippines
    June 4, 2015
    A series of transportation projects are in hand for Mindanao in the Philippines. The Philippines' Mindanao Development Authority (MinDA) has said that the Mindanao Development Corridors' major infrastructure component will cost some US$14.02 billion in all. Of the total, some $5.6 billion will be spent on airports, seaports and roads. MinDA intends that these projects will get underway out in the next two years, with work planned for completion in five years. A new bridge has been proposed that will conne