Doka delivers on the Nawaseeb Road

The Nawaseeb Road in Kuwait forms an important part of the country's national infrastructure, providing a strategic, logistical corridor to neighbouring Saudi Arabia
June 29, 2021 Read time: 3 mins

 

In delivering a solution for the highway bridge section, Doka helped provide Kuwait with a landmark achievement - its first in-situ cantilever bridge.

Doka supplied an all-in-one solution that included 3D planning, cantilever forming travellers and formwork instructors' support to ensure a smooth, fast and cost-effective process.

The 37km RA217 section of the Nawaseeb Road, also known as Route 40, is one of Kuwait's most important transport projects and part of Kuwait’s Development Plan 2015-2020. Work includes reconstruction and expansion of the highway into a six-lane dual carriageway with nine interchanges and three bridges. The design replaces U-turn points with roundabouts at all interchanges.

Doka was required to find a casting solution for the two main bridges, including pier-to-pier spans, for a combined length of 940m. The longest spans are 110m. Also, there is one 893m-long ramp bridge with a maximum span of 95m between piers. The work required 300 casting sections up to 250tonnes in weight.

Doka used its internal digital planning tools to design the solution that ensured an accelerated planning process while providing the client with an overall visual representation of the project. DokaCAD for Revit was used to produce a 3D model for a more precise visualisation of the cantilever forming travellers.

In total, six Doka Cantilever Forming Travellers, supplemented with around 2,000m² of Large-area formwork Top 50 were used on both the main bridges and ramp bridge at Interchange 5. About 825tonnes of Doka material was used.

Using Doka's Cantilever Forming Traveller, the client was reassured by its high-performance precision and how its modular components enabled it to adapt flexibly and quickly to the bridges' varying geometrics. Thanks to the system's ergonomics and a small number of separate parts, the construction process was optimised, meaning a shorter construction schedule to reduce cost.

Due to limited space onsite, hydraulic cylinders were used to strip the inner wall formwork. As the bridge deck geometry was required to be reduced at every casting step as part of the agreed planning process, the formwork and components of the traveller had to be continuously adjusted. Various hydraulic cylinders and other integrated functions allowed for an easy adjustment process without using chain hoists or additional workforce.

The Doka Cantilever Forming Traveller offers formwork and shoring from a single source with balance between support structure and formwork enabling construction of 470m of the main bridge (images courtesy Doka)
The Doka Cantilever Forming Traveller offers formwork and shoring from a single source with balance between support structure and formwork enabling construction of 470m of the main bridge (images courtesy Doka)

Doka’s Cantilever Forming Traveller uses special slide bearings to allow safe and controllable shunting while preventing unwanted movement along its longitudinal gradients. This ensured the construction team's safety in every phase of the project through fully-enclosed working platforms and an integrated ladder system at all levels.

Meanwhile, Doka’s formwork for the pier heads measured up to 20m in height, 12m in length and was erected onto Load-bearing towers d3 with Large-area formwork Top 50.

Due to the restrictions of existing gas pipelines, the piers' location was predefined, resulting in different spans that led to an im-balance in construction delivery. To support the bridge deck during this phase, Doka UniKit towers were used to safely transfer up to a maximum force of 3,800kN to restore balance to the process and ensure the safe delivery of the piers.

Doka Formwork Instructors supported onsite delivery by ensuring that the formwork was used effectively and that the operations ran smoothly from start to finish.

"In using Doka's Cantilever Forming Traveller solution, the project benefited from having an all-in-one solution that was easy for our site teams to use while remaining flexible in terms of versatility for the project's varying challenges,” said Mohamed Dackrory, deputy executive manager of Arab Contractors

For more information on companies in this article

Related Content

  • Polish bridge construction project underway
    September 30, 2019
    Construction work is underway for a new bridge forming part of the S3 expressway in Poland. The second bridge at Cigacice is close to completion and is in the Lubuskie Voivodeship, Poland. The S3 route represents a major construction project for Poland with work ongoing for the stretch connecting Sulechów and Nowa Sól. This section includes building a new bridge spanning the Odra River at Cigacice is being built. This bridge is built from either side of the river and now is almost connected and is expected
  • Brazil weighs its WIM options
    July 21, 2021
    Recent legislation in Brazil is allowing greater use of weigh-in-motion technology, all in an attempt to address some familiar challenges, writes Intercomp's Jon Arnold.
  • Next-generation materials testing with new technology
    August 17, 2022
    The US’s Balanced Mix Design sets the stage for next-generation performance testing, according to CONTROLS’ Andrea Carlessi
  • Doka chalks up sales revenue success
    January 6, 2017
    Globally renowned Austrian formwork company Doka has almost tripled its sales revenue in the last 12 years and is aiming for greater success in 2013, according to Group chairman Josef Kurzmann. Kurzmann said the firm recorded sales revenue of €853million in 2012, compared to €326million in 2000. Additionally, the percentage of non-European sales revenue accrued by Doka had increased from 6% in 2000 to 42% in 2012. To achieve further sales revenue growth, Kurzmann said Latin America, North America and India