Clever electric solution for embankment stabilisation

A highly innovative solution for road embankment stabilisation has helped save costs by up to 30% over conventional techniques. Balfour Beatty Mott MacDonald has used electrical current to stabilise embankments on a busy UK dual carriageway, avoiding disruption to motorists, cutting carbon by 40% and costs by 30%, and producing zero waste When slope failure was detected on embankments carrying the popular A21 dual carriageway, Balfour Beatty Mott MacDonald pioneered a novel technique to tackle the prob
August 28, 2013 Read time: 3 mins
The positively charged anodes were driven into the slope and negatively charged cathodes are installed into holes formed using a continuous flight auger, with the cathodes allowing drainage

A highly innovative solution for road embankment stabilisation has helped save costs by up to 30% over conventional techniques. Balfour Beatty Mott MacDonald has used electrical current to stabilise embankments on a busy UK dual carriageway, avoiding disruption to motorists, cutting carbon by 40% and costs by 30%, and producing zero waste

When slope failure was detected on embankments carrying the popular A21 dual carriageway, 1530 Balfour Beatty Mott MacDonald pioneered a novel technique to tackle the problem. This solution at Stocks Green avoided lane closure, preventing traffic disruption on the busy road, and also cut costs.

The earth embankment had been constructed with sides that were too steep and combined with poor drainage, this was causing the slopes to shear and slump. “Progressive failure would have undermined the safety barrier,” said Michael Tandy, Balfour Beatty Mott MacDonald geotechnical engineer.

Slope failure is normally tackled by replacing earth with granular material that is freer draining and better withstands loading, mixing lime into the embankment to stiffen and strengthen it, installing soil nails, or building retaining walls. All involve removing vegetation and closing traffic lanes. “The A21 is a major commuter route, so restricting the width of the road would have resulted in major congestion,” Tandy said.

Instead the firm opted to try a technique combining electro-osmosis with soil nailing and drainage, patented by its supply chain partner Electrokinetic. More than 200 years ago, it was observed that when an electrical current was passed through fine-grained material, it drew water along with it. Electrokinetic has harnessed this principle, known as, electrokinetic geosynthetics (EKG).

The company has developed a lightweight, mobile, track-mounted drilling and nailing rig, which was used to install 195 perforated steel tubes into the ground. Driven anodes were angled downward, acting like nails to hold material in place, while cathodes were inserted into pre-bored holes, sloping upward to act as drains to bring water from deep within the embankment to the surface.

Using a mobile generator, current was passed from anodes to cathodes to draw water out of the soil structure, consolidating it. “This method has been used in mining, in construction of dams and docks and on the 1211 London Underground,” Michael explains. “This was the first time the technology had been applied to a major road in the UK.”
After six weeks the drainage phase was complete and the electricity shut off. To convert the anodes into permanent soil nails, grout was injected down the tubes and forced out, through the perforations, into the surrounding ground, locking the nails firmly into the soil matrix. The drains remain permanently in place.

Work was carried out from the foot of the embankment, meaning no lane closures were required. “The approach taken by Balfour Beatty Mott MacDonald meant personnel weren’t exposed to risk from passing vehicles,” Tandy said.

The scheme has won two industry awards for innovation and sustainability. “The technology worked so well that the 2309 Highways Agency has already awarded contracts to use it elsewhere on the highways network,” Tandy said.

For more information on companies in this article

Related Content

  • Bridge surface repair improves safety
    July 9, 2012
    Modern products are making life easier for those who have to look after bridges in need of repair Aproject to repair a bridge in the American state of Tennessee has brought safety benefits and improved the ride quality for drivers using the crossing. The Chickasaw Bridge spans the Ellington Parkway and it has benefited from a rehabilitation job by contractor Jamieson Construction. The roadway on the bridge was in a poor state and required frequent patching, and to tackle the problem, the Tennessee DOT consi
  • Contract to improve UK port connectivity
    April 8, 2014
    The Mott MacDonald Grontmij joint venture (MMG JV) is now working on the contract for the technical assurance role for the A160/A180 link to the Port of Immingham. The road project is located near Grimsby in the UK and is being developed by the Highways Agency as part of the national strategic road network improvement strategy. This is one of four schemes chosen for progression under the accelerated delivery programme and aims to reduce traffic congestion, cut journey times and increase safety. Works includ
  • Lanes Group praised for helping fast-track UK jam-busting road
    October 16, 2015
    The UK drainage and maintenance specialist Lanes Group has helped deliver the new A453 dual-carriageway in the county of Nottinghamshire, one of England’s worst congestion areas. Main contractor Laing O'Rourke managed the two-and-a-half-year project that included the widened commuter route from Junction 24 of the M1 motorway to the A52 highway in Nottingham city centre at a cost of US$265 million. The new road - named Remembrance Way in honour of the 453 British soldiers who lost their lives in Afgha
  • Wirtgen: low-emission recycling near Legoland
    March 22, 2024
    Wirtgen, Vögele and Hamm were on a section of the busy E45 highway close to the famous Legoland resort at Billlund, Denmark.