Using demolition tools from Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.
July 6, 2012 Read time: 2 mins
Using Atlas Copco demolition attachments helped the fast removal of an old bridge over a busy German autobahn in a strict timeframe
Using demolition tools from 161 Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.

Near Randersacker an old bridge crossing the river Main built in 1964 was demolished using explosives and a new wider one was erected just 3m away. This new bridge is already in use.

After the 540m long Main bridge was blown up, the B13 underneath the bridge was to be re-opened to traffic in just 48 hours. This required some 1,500m3 of reinforced concrete which collapsed on this particular section of the B13 to be crushed and another 800m3 of a layer provided to protect the top surface of the road to be removed. Across the entire length of the former pre-stressed steel bridge, a total of 25,000m3 of reinforced concrete had to be taken care of.

Eight Atlas Copco hydraulic breakers with service weights from 1.2-7tonnes were used for the job by the contractor Ruppert KG Erdbau + Abbruch while six hydraulic pulverisers were used to crush the bridge fragments on the spot. Part of the bridge could not be demolished using explosives and was instead cut down using Atlas Copco CC 2500 U and CC 3300 U CombiCutters mounted on 718 Liebherr R954 and R974 long reach excavators. The B13 was already cleared after just 36 hours, so that the Federal road could be opened to traffic much earlier than scheduled.

For more information on companies in this article

Related Content

  • Breakers break up bridge in US state of Mississippi
    January 19, 2015
    A US contractor has carried out a successful demolition job on a bridge using excavators fitted with hydraulic breakers. The fleet of 178 Caterpillar excavators used for the work managed to break up the ageing structure in just 11 hours. The old Pigeon Roost road bridge will now be replaced with another, more modern structure better able to carry the necessary traffic load. The 1500 Mississippi Department of Transportation filmed the job using time lapse techniques to show the 11 hour job condensed into just 49 stunning seconds.
  • US asphalt and quarry show highlights new technology
    May 8, 2015
    New technology was one key focus area for the World of Asphalt/AGG1 event run recently in the US city of Baltimore - Mike Woof writes Technology has been a major focus for the combined World of Asphalt and AGG1 2015 exhibition and conference held in Baltimore. The exhibition area attracted 450 exhibitors and covered a larger area than for previous events, while over 10,000 education season tickets were bought by those wanting to attend the presentation sessions. The event was held from March 17th- March
  • Saudi re-opens Jadeedah Arar crossing
    December 4, 2020
    After a 50km upgrade, the Saudi road into Iraq officially re-opens.
  • Well structured maintenance
    January 4, 2013
    Major bridge maintenance and replacement projects across the world are extending the life of many impressive historic landmarks as Guy Woodford reports The Tamar Bridge, part of the main A38 trunk road linking Saltash in Cornwall with Plymouth in Devon, south west England, marked its 50th anniversary with a steel deck resurfacing project involving Stirling Lloyd's Eliminator bridge deck waterproofing system. Jointly owned by Plymouth City Council and Cornwall Council, the Tamar has a suspended length of 642