48 hours re-opening

Using demolition tools from Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.
July 6, 2012 Read time: 2 mins
Using Atlas Copco demolition attachments helped the fast removal of an old bridge over a busy German autobahn in a strict timeframe
Using demolition tools from 161 Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.

Near Randersacker an old bridge crossing the river Main built in 1964 was demolished using explosives and a new wider one was erected just 3m away. This new bridge is already in use.

After the 540m long Main bridge was blown up, the B13 underneath the bridge was to be re-opened to traffic in just 48 hours. This required some 1,500m3 of reinforced concrete which collapsed on this particular section of the B13 to be crushed and another 800m3 of a layer provided to protect the top surface of the road to be removed. Across the entire length of the former pre-stressed steel bridge, a total of 25,000m3 of reinforced concrete had to be taken care of.

Eight Atlas Copco hydraulic breakers with service weights from 1.2-7tonnes were used for the job by the contractor Ruppert KG Erdbau + Abbruch while six hydraulic pulverisers were used to crush the bridge fragments on the spot. Part of the bridge could not be demolished using explosives and was instead cut down using Atlas Copco CC 2500 U and CC 3300 U CombiCutters mounted on 718 Liebherr R954 and R974 long reach excavators. The B13 was already cleared after just 36 hours, so that the Federal road could be opened to traffic much earlier than scheduled.

For more information on companies in this article

Related Content

  • Rader Hochbrücke construction set for summer
    April 7, 2025
    Work on the Rader Hochbrücke (bridge) near Rendsburg, Germany, will start this summer and take five years, according to DEGES.
  • Wirtgen KMA 220 passes with flying colours at Cologne/Bonn Airport
    July 25, 2018
    A Wirtgen KMA 220 produces hydraulically bound base using a mix-in-plant process for recycling at Cologne/Bonn Airport. With the mobile KMA 220 mobile cold recycling mixing plant from Wirtgen, road construction materials can be recycled or upgraded in just about any location. This avoids countless transport trips and is also sustainable and environmentally friendly. Finally, it is extremely economical, according to Wirtgen. This became clear from a job at Cologne/Bonn airport at the end of 2017. The plan
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • Diefenbaker Bridge saved from tolling
    February 11, 2020
    Canada's Prince Albert city will not toll the ageing two-lane Diefenbaker Bridge