Slovakia, Salini Impreglio to part ways over D1-Višňové tunnel work

Slovakia and the Italian-Slovak consortium of Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel. The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed
March 11, 2019 Read time: 2 mins

Slovakia and the Italian-Slovak consortium of 7809 Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel.

The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed by the Slovakian government and the 1116 European Union through the 1054 European Investment Bank.

Slovakia’s National Highway Company (5891 NDS) has been under heavy criticism over construction delays and cost projections for the work that was scheduled to be finished by the end of this year. According to Slovakian media, the consortium has three months to wrap up its work but has also agreed to pay money owed to subcontractors through a new bank guarantee.

Michaela Michalová, a spokesman for NDS, said a new contractor will emerge from a transparent competition in the coming months.

"It is our goal to complete the project by 2023 because it is financed with [European Union] funds," said Árpád Érsek, transport minister, as quoted by the Slovak News Agency SITA.

The original design and build contract was worth about €410 million when signed in 2014, according the a statement Salini Impregilo at the time. Construction was expected to take five and half years.

For more information on companies in this article

Related Content

  • Slovakia’s D1 Budimir-Bidovce motorway stretch gets EU backing
    November 2, 2018
    Slovakia’s motorway company NDS and the Transport Ministry have agreed a subsidy of nearly €204 million for a D1 section. The EU will cover 85% of the project cost, while the remaining 15% will be covered by the government for construction the 14.5km D1 motorway between Budimir and Bidovce, near the city of Kosice. The section, being built by Skanska for almost €237 million, is on schedule for completion by the end of 2019. The stretch will be part of the eastern by-pass of Kosice and in Budimir it wi
  • Tunnel Boom in Central and Eastern Europe
    September 15, 2015
    Following the success of the 41st World Tunnel Congress held in Croatia last May, World Highways looks at two signi_ cant projects in Slovakia and Serbia – Adriana Potts reports Central and Eastern Europe is buzzing with a number of major projects being developed - including highways, bridges and tunnels – and with many more in the pipeline. The region is expected to be highly active with plans for developing infrastructure in the next two decades, according to Davorin Koli , president of the Croatian
  • Upgrade of Slovakia’s busy D1 stretch to start in H2 2014
    March 19, 2014
    Slovak national motorway company NDS plans to start the reconstruction and modernisation of the D1 motorway section between Bratislava and Trnava in H2 2014. As part of the near €150 million project, the current six-lane motorway will be extended by adding an emergency lane. The building works are expected to last 24 months and will include demolition and reconstruction of some of the existing road bridges, as well as construction of new ones. The motorway lanes will be extended from the current 3.5m to 3.
  • Slovak government stands firm over R2 Expressway, including Soroska Tunnel
    August 11, 2017
    Jan Durisin, head of Slovakia’s motorway operator NDS, has said that the R2 expressway, will go ahead despite watchdog fears of poor value for money. Completion of the R2, that includes the Soroska Tunnel, remains 2024, he told Slovakian news agencies. NDS, he said, will start looking for a contractor to start work in 2018 on a stretch of the expressway near the town of Roznava. R2 is a 360km route that will run from Kosice in the east across the country to Trenčín, near the Czech border in the west. It wil