Grimsby’s Corporation Bridge work extended

Refurbishment of the nearly 100-year-old bascule bridge in northern England is being done by Spencer Group with project management by Equans.
By David Arminas March 6, 2024 Read time: 3 mins
Corporation Road Bridge is a relatively rare Scherzer rolling lift bascule bridge (image courtesy Grimsby City)

More refurbishment work than at first thought is needed after grit blasting finished on the Corporation Road Bridge in Grimsby, northern England.

Grit blasting to the undersides of the bascule bridge, nearly 100 years old, for spans one through four allowed a detailed inspection of the structure. The timber lifting deck was removed and a temporary deck installed while work continues, according to the Spencer Group, the principal contractor on the project and which has carried out maintenance and repair work on some of the UK’s most iconic bridges, including the Humber, Forth, Erskine, Severn and Menai bridges.

Harsh environmental conditions, including the salt water of the Alexandra Dock water over which the bridge crosses, has led to higher degradation of the steel structure than expected. This has required further designs to be added to the scope of works in addition to further physical repairs.

Steel repair work has begun both above and below deck, with painting work progressing as repairs permit.

(image courtesy Invest North East Lincolnshire - Investel)

Encapsulation and scaffolding are now fully erected to the north side of spans five and six above deck, preventing dust, debris and adverse weather from affecting the work in progress. Grit blasting is progressing on these sections as well.

Detailed design work to the bridge lifting control room has now been completed with work due to start in the next few weeks, according to the client, North East Lincolnshire Council.

Restoration work including structural renovation and aesthetic improvements started in February last year on the heritage listed bridge and will cost around €5 million. Spencer Group said the bridge will remain open to pedestrians and cyclists, except during short periods when the contractor will need to test the lifting mechanisms and the bridge will need to be fully closed.

Equans, part of the Bouygues Group, is project manager for the work which are expected to take 11 months to complete.

Corporation Road Bridge is a relatively rare Scherzer rolling lift bascule bridge, as noted by Equans. The rolling lift trunnion - sometimes a Scherzer rolling lift bridge raises the span by rolling on a track resembling a rocking-chair base. The Scherzer rolling lift is a refinement patented in 1893 by American engineer William Donald Scherzer.

The Grimsby bridge was built in 1928 to replace an existing swing span bridge to allow shipping traffic access to the former fishing dock from inland waters. Although little shipping uses the river, undertaking the works will allow the bridge to be removed from the “heritage-at-risk” register.

“The bridge is a key structure the borough and these works will help to protect this landmark for many years to come and preserve its Grade II listed heritage status,” said Neil Foster, Equans’ project manager on the North East Lincolnshire contract.

To keep up to date with the Corporation Road Bridge works, click here.

For more information on companies in this article

Related Content

  • Colas UK takes Covid-19 precautions as it starts on Lincoln road contract
    April 8, 2020
    Colas is providing routine and emergency repairs for traffic signals in Lincolnshire county.
  • The UK’s Humber Bridge gets protected status
    July 28, 2017
    Any refurbishments to the Humber Bridge near the northern English city of Hull will be subject to intense scrutiny after being designated a historic site. The bridge - only 36-years old – was the longest single-span suspension bridge for 16 years until it was surpassed in 1998 with completion of Japan’s Akashi Kaikyō Bridge with a main span of 1.9km. The Humber Bridge now ranks eighth-longest as measured by its main span of 1.4km. Historic England, the listed structures designating authority, described the
  • Europe closes in on the crossings
    September 27, 2017
    The Mersey Gateway bridge project off England’s west coast passed a milestone recently with the first joining of two of the deck sections. The key segments, as the sections are called, link the north approach viaduct to the north pylon deck span and are the first of four deck-joins scheduled for this summer. In total, there are five sections of bridge deck and approach roads that need to be joined.
  • Brokk offers painless bridge work
    February 10, 2020
    Peter Bigwood* makes the case for using remote-controlled demolition machines to demolish bridge decks