Solution found for Colombian tunnel project?

A solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover. The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity r
March 12, 2015 Read time: 2 mins
RSSA solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover.

The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity recommence, according to Business News Americas. The US$363 million project has been the focus for major negotiations between both parties over the last few months while a solution has been searched for. Earlier this year, work stalled and the consortium faced having its contract cancelled by the state road authority 2812 Invias. Meanwhile the consortium members were told they could face a ban from working on any state tenders for a five year period.

The Segundo Centenario consortium comprises 11 firms: Condux, Constructora Herreña Fronpeca Colombia, Álvarez y Collins, Constructora Carlos Collis, Constructora Montecarlo Vías, Túneles de Colombia, Construirte, Gaico Ingenieros Constructores, H&H Arquitectura and Feluca.

This new compromise deal means that the consortium has to complete the tunnel by the end of November 2016. An additional $125 million is being provided to pay for the completion work. The 8.5km tunnel will link Colombia’s capital Bogota with the country’s main port, Buenaventura, and was originally planned for completion by November 2014. The tunnel is around 75% complete and the project also includes the construction of a 24km highway. When the route is finished it will cut journey times for commuters and also for the many heavy trucks driving between the port and Bogota, as well as improving safety over the existing road.

For more information on companies in this article

Related Content

  • Key Colombian highway under construction
    June 23, 2021
    A key Colombian highway project is now under construction.
  • Funding issue for Bangladesh tunnel but highway moving forward
    November 14, 2017
    Two major infrastructure projects in Bangladesh are experiencing rather different fates at present. A lack of suitable funding has resulted in the US$705 million Karnaphuli river tunnel project coming to a grinding halt. However the $1.53 billion contract for the Dhaka to Ashulia highway has now been awarded to the Chinese firm, China National Machinery Import and Export Corp (CMC). Chinese funding is intended to pay for the Karnaphuli Tunnel, but has so far been delayed and the Chinese contractor awarded
  • East Africa’s massive new ring road project
    June 30, 2016
    Plans are being drawn up for a major new highway project in East Africa. Preparations are being made by the authorities in Kenya, Uganda and Tanzania. The 450km ring road route runs around the shoreline of Lake Victoria and will provide better transport connections for Kenya, Uganda and Tanzania, as well as for other near neighbours, particularly Rwanda and Burundi. New border posts will be required, to help increase the flow of traffic between the nations. Although it will be complex, the project will boos
  • Sandvik’s Turkish delight at groundbreaking tunnel vision
    May 20, 2014
    Turkey’s longest, and what will be the world’s fourth longest, highway tunnel is being built under Mount Ovit in the northeast of the country. Sandvik Construction is playing a vital role in the construction of the giant new structure, which will enable all-year-round access to what is a relatively remote and often snow-blocked part of Anatolia Having had their freedom of movement blighted for many years by wintertime snow blocking the D925 highway, along with narrower roads and passes, at Mount Ovit, resi