Solution found for Colombian tunnel project?

A solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover. The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity r
March 12, 2015 Read time: 2 mins
RSSA solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover.

The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity recommence, according to Business News Americas. The US$363 million project has been the focus for major negotiations between both parties over the last few months while a solution has been searched for. Earlier this year, work stalled and the consortium faced having its contract cancelled by the state road authority 2812 Invias. Meanwhile the consortium members were told they could face a ban from working on any state tenders for a five year period.

The Segundo Centenario consortium comprises 11 firms: Condux, Constructora Herreña Fronpeca Colombia, Álvarez y Collins, Constructora Carlos Collis, Constructora Montecarlo Vías, Túneles de Colombia, Construirte, Gaico Ingenieros Constructores, H&H Arquitectura and Feluca.

This new compromise deal means that the consortium has to complete the tunnel by the end of November 2016. An additional $125 million is being provided to pay for the completion work. The 8.5km tunnel will link Colombia’s capital Bogota with the country’s main port, Buenaventura, and was originally planned for completion by November 2014. The tunnel is around 75% complete and the project also includes the construction of a 24km highway. When the route is finished it will cut journey times for commuters and also for the many heavy trucks driving between the port and Bogota, as well as improving safety over the existing road.

For more information on companies in this article

Related Content

  • Colombia’s ANI agency is driving forward the 4G PPP programme
    April 4, 2016
    Andrade Moreno is a man on a mission. The head of Colombia's infrastructure agency ANI explains how the organisation is giving foreign companies increasing confidence to invest time and money in the country. David Arminas reports Change, especially when it touches the highest levels of South American business and politics, can bring with it personal danger. Luis Fernando Andrade Moreno, president of Colombia's National Infrastructure Agency - ANI - was aware of this when he took on the role in 2011. B
  • Delay for tenders on key Colombian highways
    April 28, 2014
    The tender process has been extended for three highway concession packages in Colombia, according to Business News Americas. The country's national infrastructure agency (ANI) has extended the bid deadlines for the Pacífico 2 (Bolombolo-La Pintada), Pacífico 3 (La Pintada-La Virginia) and Río Magdalena 2 (Remedios-Puerto Berrío) projects. The three highway concessions are worth a total of US$1.2 billion and form part of Colombia’s Autopistas para la Prosperidad highway programme. ANI opted to delay the tend
  • Bolivian Government to invest US$129.3mn in Moxos-Trinidad road
    October 31, 2013
    A project to improve Bolivia’s existing 77.8km road between San Ignacio de Moxos and Trinidad will cost US$129.3 million, the government has announced. The project includes a 1.7km bridge over Mamore river. The first areas of work will involve the road between San Ignacio de Moxos and Puerto Ganadero. This section will cost US$84 million and will be improved by ABC. Euroestudios-CPS Belmonte has signed a US$2.2 million contract with ABC for studies on the future Mamore river bridge. The cost of the bridge h
  • Negotiations continue on Algeria’s east-west motorway
    July 31, 2015
    Algeria’s Minister of Public Works, Abdelkader Ouali, has told the state of El Taref that negotiations between his department via the national agency of highways (ANA) and the COJAAL consortium for the completion of the construction of the country’s east-west expressway are progressing well. Negotiations between the two parties should continue in order to find technical solutions and financial adjustment, he said. He also announced that the public group Cosider has been selected to reinforce companie