Colombia’s delayed La Linea Tunnel and tertiary road development programme seeing progress

Progress is now being seen in Colombia with regard to key tunnel and road projects. A consortium comprising Conconcreto and CSS Constructores is to complete the 12% of work still needed to finish the La Linea Tunnel project.
July 6, 2017 Read time: 2 mins
RSS

Progress is now being seen in Colombia with regard to key tunnel and road projects. A consortium comprising Conconcreto and 3222 CSS Constructores is to complete the 12% of work still needed to finish the La Linea Tunnel project. The consortium is called Consorcio La Linea and the US$73.8 million deal was awarded by the National Road Institute (2812 Invias). The consortium will have to complete work on the delayed project by 2018. In addition, Consorcio La Linea will also build a second lane on the Calarca and Cajamarca stretch of road.

The La Linea Tunnel project has suffered from a catalogue of woes since it was planned, with a series of delays and stoppages for a diverse array of reasons. These have included problems arising from unexpectedly challenging geological conditions as well as the wrong kind of insurance cover for the project. The latest in the sorry series of delays occurred when Colombian contractor Constructora Carlos Collins stopped its work on the project earlier this year, resulting in a new tender being required to finish the construction of the tunnel.

Overall, the consortium is expected to finish the pre-construction stage by August 2017, before submitting final studies and designs in late September 2017. Consequently, the project developer will be required to assess the existing works and complete all preparations before the end of November 2017.

Meanwhile work is continuing on the plan to upgrade 2,500km of tertiary roads across the country. Funding worth some $427.4 million looks likely to be diverted towards road development, with this having been reassigned from the Science, Technology and Innovation Fund. The Colombian Government has yet to finalise this process. In addition, 3213 Colombia's National Planning Department (DNP) has also released a report on the rural road development plan. The DNP's calculations reveal that additional funding will be required to pay for a further 900km of work required. The funding available so far could only finance 1,600km of the roads needing repairs and improvements and scheduled between 2017 and 2018. Colombia's Transport Ministry has said that it will set up a priority list of the most important routes needing improvement work. The tender processes will then be established in line with the regulations from Invias.

For more information on companies in this article

Related Content

  • Key highway project in Colombia faces delay
    December 2, 2013
    Work on a key stretch of Colombia’s Ruta del Sol highway project is behind schedule, with the route now unlikely to open to traffic before 2017. The 21.6km section of the highway facing these delays will link Villeta and Guaduas in Cundinamarca. A key challenge is technical as the US engineering firm Gall Zeidler Consultants has warned Colombia’s infrastructure agency (ANI) that this section of the route is geologically unstable. The proposed route could be at risk from slippage and will need to be stabilis
  • Financing found for Colombian key construction contract
    December 19, 2017
    Financing has now been secured for a key highway project in Colombia. The project is for the Bogota-Girardot 4G road concession, with a loan from Colombia's national development bank, Financiera de Desarrollo Nacional (FDN), providing the necessary financing.
  • Colombian tunnel project faces further delays
    September 16, 2014
    The Colombian Government is looking to cancel the contract for the construction of the La Linea tunnel. This project has already been beset by an array of problems since it was first conceived and now looks set to be further delayed. Work was supposed to have been 20% complete by March 2014, however a series of delays had put the project far behind schedule and by March 2014, only 12% of the work had been carried out. In June 2014, the project was supposed to be 50% complete, but work was in fact just 14% h
  • Colombia’s Tunel de Oriente delay
    August 20, 2018
    The construction of Colombia’s Tunel de Oriente project is running behind schedule. Unexpected geological problems are the reason for the delay to the project’s completion. However the builders have assured the client that the delay will not increase the cost of the project. The tunnel, located in Colombia’s Antioquia Department, was due for completion in December 2018 but will now be ready by May 2019.