Argentina upgrading roads to highways

Argentina’s Government has plans to upgrade Route 5, Route 7 and Route 8 into highways. The work will cost US$647.2 million and the first sections are already being completed. Around 210km of Route 7 will be upgraded to a highway while a 165km stretch of Route 8 will be upgraded to a highway. The work on Route 8 will reach Solis in 2017 and Pergamino in 2019, while Route 5 will be turned into a highway between Lujan and Bragado, with the work due for completion in 2019.
March 7, 2016 Read time: 1 min
Argentina’s Government has plans to upgrade Route 5, Route 7 and Route 8 into highways. The work will cost US$647.2 million and the first sections are already being completed. Around 210km of Route 7 will be upgraded to a highway while a 165km stretch of Route 8 will be upgraded to a highway. The work on Route 8 will reach Solis in 2017 and Pergamino in 2019, while Route 5 will be turned into a highway between Lujan and Bragado, with the work due for completion in 2019.

Related Content

  • Bolivia highway upgrade project planned
    March 3, 2016
    Work on a new dual lane highway connecting La Paz with Santa Cruz in Bolivia is set to cost US$1 billion. The work will be complete by 2019 and the route will link La Paz with Santa Cruz, running through Cochabamba. The Bolivian Ministry of Public Works says that this project will be carried out in addition to previous developments to the road system between La Paz and Oruro. The project to connect different regions includes the 28km double lane highway for El Sillar, as well as tunnels and viaducts. This
  • Key highway project in Colombia faces delay
    December 2, 2013
    Work on a key stretch of Colombia’s Ruta del Sol highway project is behind schedule, with the route now unlikely to open to traffic before 2017. The 21.6km section of the highway facing these delays will link Villeta and Guaduas in Cundinamarca. A key challenge is technical as the US engineering firm Gall Zeidler Consultants has warned Colombia’s infrastructure agency (ANI) that this section of the route is geologically unstable. The proposed route could be at risk from slippage and will need to be stabilis
  • Paraguay road tender opening
    March 18, 2019
    The tender process for the second section of Paraguay’s bi-oceanic highway project is commencing in mid-2019. This 573km stretch of highway is being offered in two sections, with financing likely to come from international banks. The consortium Consorcio Corredor Vial Bioceanico is handling the first section of the project, which is costing around US$443.4 million. The second section of the route is expected to cost $800 million. The third stretch of the route will be complex as it includes a new bridge spa
  • Chile-Argentina tunnel project to take nine years
    May 3, 2017
    Construction work for the Agua Negra tunnel connecting Argentina with Chile is expected to take nine years to complete. The actual construction work will commence in 2019, although considerable activity will be required beforehand. Building the tunnel is expected to cost in the orders of US$1.5 billion. Much of the financing for the project is being provided by the Inter-American Development Bank (IADB). So far the IADB has given $20 million to Argentina and a further $20 million to Chile to pay for the nec