Algeria to engage Japanese government over dispute with Cojaal

The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal, In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.
January 14, 2015 Read time: 3 mins
The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal,

In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.

The East-West Highway runs along the Mediterranean area of Algeria, with the eastern section running from the province of Bourdj Bou Arreridj to the Tunisian border. The road will drastically reduce the time of up to three days to drive across northern Algeria.

Cojaal - the Consortium Japonais Pour l'Autoroute Algérienne - is a joint venture comprising five of Japan’s largest companies: Japan’s two largest contractors 2809 Kajima and 2808 Taisei, general contractors 2811 Hazama and Nishimatsu as well as the trading house 4081 Itochu.

According to %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal information from Kajima Visit www.kajima.com Website false http://www.kajima.com/news_events/special_features/vol2/vol2-1.html false false%>, Cojaal was to build a six-lane motorway with three lanes on each side, 43 bridges on the main route and three tunnels. “It is one of the largest infrastructure projects ever to be undertaken by Japanese companies outside of Japan,” Kajima said at the time of the contract award.

Completion of the entire East-West Highway was originally scheduled for 2010 and most of it is completed, except for the eastern section, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17854 0 oLinkExternal as reported Visit WH Story Page false /categories/road-highway-structures/news/work-to-restart-on-key-algerian-highway-section/ false false%> by 3260 World Highways in June. But last October, Algeria’s Minister of Public Works Abdelkader Kadi terminated the contract with Cojaal to build the eastern section’s final 84km after a part of the Djebel el Ouahch tunnel in Constantine constructed by COJAAL collapsed in January last year.

Algerian Press Service reported that Kadi said the last stretch of the eastern section will be awarded to other companies, but he gave no details of which firms stood to gain the work.

Kadi also said he was confident that a satisfactory outcome for both parties will be agreed before June. However, he noted that he was also confident that Cojaal would recognise its responsibility for the delays to work over several years and the tunnel problems.

Kadi confirmed that a 13km bypass, costing nearly $57 million, is being built to resolve traffic problems due to the collapse of the tunnel and should be operational by June.

For more information on companies in this article

Related Content

  • Accurate load weighing system from Loadrite
    February 13, 2013
    The Loadrite L2150 wheeled loader bucket weighing system is said to offer increased accuracy and reliability. The system is said to ensure haul trucks can be loaded properly, improving overall productivity by ensuring operational efficiency. Using this weighing system trucks are neither under-loaded nor over-loaded, with the ensuing associated productivity losses and excess machine wear problems respectively, all but eliminated. Aimed at use in large quarry operations the new Loadrite L2150 unit is said to
  • Poland’s GDDKiA promises to improve road procurement processes
    January 12, 2015
    The Polish national roads authority GDDKiA has said that it will no longer look for the cheapest offer in road-building tenders. Instead, it will, in line with European Union requirements, consider whole life cycle factors such as durability, cost of exploitation and quality. Poland has long been criticised by the road construction industry, both within the country and in the rest of Europe, for handing out tender wins to the lowest bidder with scant regard for life-cycle costs. The government has also b
  • Bell launches high-manoeuvrability 4x4 ADT for narrow bench work
    April 15, 2013
    Bell has introduced a 4x4 version of its B30D articulated dump truck (ADT). The machine has the front chassis, cab and engine of the standard 6x6 but comes with a shortened rear chassis and a single axle. According to Neville Paynter, managing director of Bell UK, the machine’s short wheelbase reduces the turning circle by around 25%, making it ideal for use in underground mining and on narrow benches.
  • US: Missouri state bridge repairs run out of gas
    September 11, 2015
    The US state of Missouri said it is fighting a losing battle to maintain its 641 bridges that are listed in critical condition - one-step away from being closed to traffic. Engineers in the southern state’s department of transportation said around US$820 million is needed to repair or replace the 641 bridges, three of which were closed to traffic last year. The critical list has expanded with the addition of 50 more bridges since last year. And the critical list is expected to grow to around 1,500 bri