Algeria to engage Japanese government over dispute with Cojaal

The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal, In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.
January 14, 2015 Read time: 3 mins
The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal,

In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.

The East-West Highway runs along the Mediterranean area of Algeria, with the eastern section running from the province of Bourdj Bou Arreridj to the Tunisian border. The road will drastically reduce the time of up to three days to drive across northern Algeria.

Cojaal - the Consortium Japonais Pour l'Autoroute Algérienne - is a joint venture comprising five of Japan’s largest companies: Japan’s two largest contractors 2809 Kajima and 2808 Taisei, general contractors 2811 Hazama and Nishimatsu as well as the trading house 4081 Itochu.

According to %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal information from Kajima Visit www.kajima.com Website false http://www.kajima.com/news_events/special_features/vol2/vol2-1.html false false%>, Cojaal was to build a six-lane motorway with three lanes on each side, 43 bridges on the main route and three tunnels. “It is one of the largest infrastructure projects ever to be undertaken by Japanese companies outside of Japan,” Kajima said at the time of the contract award.

Completion of the entire East-West Highway was originally scheduled for 2010 and most of it is completed, except for the eastern section, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17854 0 oLinkExternal as reported Visit WH Story Page false /categories/road-highway-structures/news/work-to-restart-on-key-algerian-highway-section/ false false%> by 3260 World Highways in June. But last October, Algeria’s Minister of Public Works Abdelkader Kadi terminated the contract with Cojaal to build the eastern section’s final 84km after a part of the Djebel el Ouahch tunnel in Constantine constructed by COJAAL collapsed in January last year.

Algerian Press Service reported that Kadi said the last stretch of the eastern section will be awarded to other companies, but he gave no details of which firms stood to gain the work.

Kadi also said he was confident that a satisfactory outcome for both parties will be agreed before June. However, he noted that he was also confident that Cojaal would recognise its responsibility for the delays to work over several years and the tunnel problems.

Kadi confirmed that a 13km bypass, costing nearly $57 million, is being built to resolve traffic problems due to the collapse of the tunnel and should be operational by June.

For more information on companies in this article

Related Content

  • Serbia in talks with Shandong Hi-Speed and China Road and Bridge
    October 22, 2014
    Talks are underway between the Serbian Ministry of Construction, Transport and Infrastructure and two Chinese companies for construction and maintenance the two sections of the Belgrade-Pozega part of the E-763 motorway. The two Chinese companies, Shandong Hi-Speed Group and the China Road and Bridge Corporation (CRBC), are hoping to build the 18km stretch between Surcin and Obrenovac, the 31km between Preljina and Pozega and the 103km between Obrenovac and Preljina. No value of the work has been conf
  • Denmark to create Rodby port to service Fehmarn Belt construction
    January 6, 2015
    The Danish government said it will create a large port area east of the small town of Rødbyhavn to facilitate construction of the future Fehmarn Belt tunnel link. The US$7.5 billion project is an 18km tunnel including two railway tunnels, two motorway tunnels and an emergency tunnel. Construction start is scheduled for later this year and should take between six and seven years. The tunnel is part of the major infrastructure project called the Fehmarn Belt Fixed Link to connect the German island of Fe
  • Angry wife tells husband it’s over with a message on a freeway billboard
    October 9, 2015
    Billboards are used to advertise everything, from toothpaste to airplanes and also to get a message across, such as don’t litter the highway. But one wife in Sheffield, United Kingdom, decided to make it personal, and tell her cheating husband that it was all over.
  • Cost rises again for Columbia’s unfinished La Linea tunnel
    February 3, 2015
    Columbia’s transport minister has said it will take nearly US$168 million and more than two years to finish the controversial La Linea tunnel. Natalia Abello Vives said the government has a “plan B” to finish the 8.65km tunnel, which, as World Highways reported in May, has less than a kilometre remaining to be constructed. It was originally scheduled to be open by last November. The La Linea tunnel project, or Segundo Centenario tunnel, crosses the central mountain range and forms part of the Bogota-B