Algeria to engage Japanese government over dispute with Cojaal

The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal, In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.
January 14, 2015 Read time: 3 mins
The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal,

In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.

The East-West Highway runs along the Mediterranean area of Algeria, with the eastern section running from the province of Bourdj Bou Arreridj to the Tunisian border. The road will drastically reduce the time of up to three days to drive across northern Algeria.

Cojaal - the Consortium Japonais Pour l'Autoroute Algérienne - is a joint venture comprising five of Japan’s largest companies: Japan’s two largest contractors 2809 Kajima and 2808 Taisei, general contractors 2811 Hazama and Nishimatsu as well as the trading house 4081 Itochu.

According to %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal information from Kajima Visit www.kajima.com Website false http://www.kajima.com/news_events/special_features/vol2/vol2-1.html false false%>, Cojaal was to build a six-lane motorway with three lanes on each side, 43 bridges on the main route and three tunnels. “It is one of the largest infrastructure projects ever to be undertaken by Japanese companies outside of Japan,” Kajima said at the time of the contract award.

Completion of the entire East-West Highway was originally scheduled for 2010 and most of it is completed, except for the eastern section, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17854 0 oLinkExternal as reported Visit WH Story Page false /categories/road-highway-structures/news/work-to-restart-on-key-algerian-highway-section/ false false%> by 3260 World Highways in June. But last October, Algeria’s Minister of Public Works Abdelkader Kadi terminated the contract with Cojaal to build the eastern section’s final 84km after a part of the Djebel el Ouahch tunnel in Constantine constructed by COJAAL collapsed in January last year.

Algerian Press Service reported that Kadi said the last stretch of the eastern section will be awarded to other companies, but he gave no details of which firms stood to gain the work.

Kadi also said he was confident that a satisfactory outcome for both parties will be agreed before June. However, he noted that he was also confident that Cojaal would recognise its responsibility for the delays to work over several years and the tunnel problems.

Kadi confirmed that a 13km bypass, costing nearly $57 million, is being built to resolve traffic problems due to the collapse of the tunnel and should be operational by June.

For more information on companies in this article

Related Content

  • ARTBA launching student video competition for 2015
    February 18, 2015
    The American Road & Transportation Builders Association (ARTBA) is running its annual student video competition. This is set up to challenge students of all ages to produce a two-to-four minute video about America’s transportation infrastructure. World Highways continues to support this competition and has also posted links to those videos from past winners and runners up on its websites in previous years. The ARTBA Student Video Competition is now in its fifth year. The aim of the competition is to raise a
  • Tata Steel invests for growth
    January 6, 2017
    Tata Steel is aiming to double its worldwide steel sales by 2017 in the lifting and excavating sector from its current volume of 500,000tonnes. To achieve this target the company has recently invested €40million to improve its product portfolio, by developing its quenched and tempered, and advanced downstream processing facilities in the UK. Tata Steel said it delivers a wider range of differentiated steel products to the lifting and excavating industry than any other steel producer in the world, and provid
  • Tata Steel invests for growth
    April 18, 2013
    Tata Steel is aiming to double its worldwide steel sales by 2017 in the lifting and excavating sector from its current volume of 500,000tonnes. To achieve this target the company has recently invested €40million to improve its product portfolio, by developing its quenched and tempered, and advanced downstream processing facilities in the UK. Tata Steel said it delivers a wider range of differentiated steel products to the lifting and excavating industry than any other steel producer in the world, and provid
  • Hillhead 2020 in the England will be even bigger than the 2018 event
    July 26, 2019
    On the back of a record-breaking event in 2018 the organisers of the UK’s Hillhead Exhibition have extended the event once again for 2020. The 2018 event was supported by 546 exhibitors and attracted an independently audited attendance of nearly 20,000. With outdoor space on track to be sold out by late autumn, an additional 2,200m² of stand space has been created in the quarry floor by extending the showground into the quarry face demonstration area. Hillhead 2020 takes place from 23–25 June, 202