Algeria to engage Japanese government over dispute with Cojaal

The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal, In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.
January 14, 2015 Read time: 3 mins
The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal,

In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.

The East-West Highway runs along the Mediterranean area of Algeria, with the eastern section running from the province of Bourdj Bou Arreridj to the Tunisian border. The road will drastically reduce the time of up to three days to drive across northern Algeria.

Cojaal - the Consortium Japonais Pour l'Autoroute Algérienne - is a joint venture comprising five of Japan’s largest companies: Japan’s two largest contractors 2809 Kajima and 2808 Taisei, general contractors 2811 Hazama and Nishimatsu as well as the trading house 4081 Itochu.

According to %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal information from Kajima Visit www.kajima.com Website false http://www.kajima.com/news_events/special_features/vol2/vol2-1.html false false%>, Cojaal was to build a six-lane motorway with three lanes on each side, 43 bridges on the main route and three tunnels. “It is one of the largest infrastructure projects ever to be undertaken by Japanese companies outside of Japan,” Kajima said at the time of the contract award.

Completion of the entire East-West Highway was originally scheduled for 2010 and most of it is completed, except for the eastern section, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17854 0 oLinkExternal as reported Visit WH Story Page false /categories/road-highway-structures/news/work-to-restart-on-key-algerian-highway-section/ false false%> by 3260 World Highways in June. But last October, Algeria’s Minister of Public Works Abdelkader Kadi terminated the contract with Cojaal to build the eastern section’s final 84km after a part of the Djebel el Ouahch tunnel in Constantine constructed by COJAAL collapsed in January last year.

Algerian Press Service reported that Kadi said the last stretch of the eastern section will be awarded to other companies, but he gave no details of which firms stood to gain the work.

Kadi also said he was confident that a satisfactory outcome for both parties will be agreed before June. However, he noted that he was also confident that Cojaal would recognise its responsibility for the delays to work over several years and the tunnel problems.

Kadi confirmed that a 13km bypass, costing nearly $57 million, is being built to resolve traffic problems due to the collapse of the tunnel and should be operational by June.

For more information on companies in this article

Related Content

  • Nice in 2018: The Pavement Preservation & Recycling Summit (PPRS)
    November 17, 2017
    Siobhan McKelvey, president of the Paris-based International Bitumen Emulsion Federation (IBEF), explains the importance for attending next year’s Pavement Preservation & Recycling Summit. The event will be held in Nice in southern France from 26-28 March at the Nice Acropolis. One of the highlights for me that is provided by the PPRS platform is the opportunity to exchange on communication experiences throughout the world and how the challenges of promoting the role of a good road network are met.
  • World Highways contributor Max Lay wins Peter Nicol Russell award
    December 9, 2014
    The Institution of Engineers Australia has awarded World Highways contributor Dr Maxwell Lay the prestigious Peter Nicol Russell medal for his contribution to science and engineering. According to the citation, the medal is the most prestigious award made by the institution. “The recipient represents the technical, professional and community service standards of engineering to the profession and the community.” May received degrees at Melbourne University and the US university Lehigh in Pennsylvania.
  • Liebherr 150EC-B is latest flat-top crane
    February 7, 2013
    Liebherr will show a modular design flat-top tower crane in the 150EC-B at this year’s Bauma. The 150EC-B is available in FR.tronic, with traditional contractor controls, or Litronic version with programmable logic controls. The flat-top crane can be had in 6 tonne and 8 tonne versions, with a maximum hook height of 63m and maximum working radius of 60m. Lift capacity at full radius is 1,700kg.
  • Penta’s custom-made plant flexibility
    April 8, 2013
    Penta Automazioni Industriali says it began trading in 1991 in response to increased demand for automation in the handling, stacking, sorting and ageing of concrete elements. The company provides custom-made plants and, through a close relationship with customers, Penta says it is able to continuously improve its products and adapt them to constantly changing market demands.