Algeria to engage Japanese government over dispute with Cojaal

The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal, In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.
January 14, 2015 Read time: 3 mins
The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal,

In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.

The East-West Highway runs along the Mediterranean area of Algeria, with the eastern section running from the province of Bourdj Bou Arreridj to the Tunisian border. The road will drastically reduce the time of up to three days to drive across northern Algeria.

Cojaal - the Consortium Japonais Pour l'Autoroute Algérienne - is a joint venture comprising five of Japan’s largest companies: Japan’s two largest contractors 2809 Kajima and 2808 Taisei, general contractors 2811 Hazama and Nishimatsu as well as the trading house 4081 Itochu.

According to %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal information from Kajima Visit www.kajima.com Website false http://www.kajima.com/news_events/special_features/vol2/vol2-1.html false false%>, Cojaal was to build a six-lane motorway with three lanes on each side, 43 bridges on the main route and three tunnels. “It is one of the largest infrastructure projects ever to be undertaken by Japanese companies outside of Japan,” Kajima said at the time of the contract award.

Completion of the entire East-West Highway was originally scheduled for 2010 and most of it is completed, except for the eastern section, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17854 0 oLinkExternal as reported Visit WH Story Page false /categories/road-highway-structures/news/work-to-restart-on-key-algerian-highway-section/ false false%> by 3260 World Highways in June. But last October, Algeria’s Minister of Public Works Abdelkader Kadi terminated the contract with Cojaal to build the eastern section’s final 84km after a part of the Djebel el Ouahch tunnel in Constantine constructed by COJAAL collapsed in January last year.

Algerian Press Service reported that Kadi said the last stretch of the eastern section will be awarded to other companies, but he gave no details of which firms stood to gain the work.

Kadi also said he was confident that a satisfactory outcome for both parties will be agreed before June. However, he noted that he was also confident that Cojaal would recognise its responsibility for the delays to work over several years and the tunnel problems.

Kadi confirmed that a 13km bypass, costing nearly $57 million, is being built to resolve traffic problems due to the collapse of the tunnel and should be operational by June.

For more information on companies in this article

Related Content

  • VIDEO: Barcelona wheelchair user weaving in traffic, passes cars
    July 25, 2016
    A wheelchair-bound man in Spain has been caught on camera weaving in and out of Barcelona traffic and moving faster than surrounding vehicles. The street racer was cruising along Barcelona's Carrer de Muntaner when a motorcycle passenger took the video. You Tube videos of speeding wheel chair users are becoming more common. But so too are videos of people who generally want more mobility out their wheelchair. So click here to see a more sensible way to live life in your wheelchair in the fast lane. Appa
  • Uzbekistan targets of 2,700km of new highways by 2019
    September 30, 2015
    Uzbekistan plans to build around 2,700km of roads by 2019 at a cost of around US$590 million. Around 2,280km will have a bituminous concrete surface and 418km will be a concrete surface. In July, the World Bank said it will grant Uzbekistan a $200 million loan for 25 years towards paying for the $240 million Regional Roads Development project that is scheduled to be completed by 2021, according to UzDaily.uz. Uzbekistan’s government also reported that around 117km roads were built in the first half
  • Hidromek is developing wheeled loaders
    February 6, 2013
    Hidromek is commencing work on developing its new wheeled loader line. Export manager Anil Bingöl said, “We have started our wheeled loader project and we hope to have our first prototype machine this year.” This will feature a 3m3 bucket and will be the first in a range of wheeled loaders from the firm. Machines with bucket capacities of 4m3 and then 5m3 will be developed in due course. Testing of the first prototype will be carried out in Turkey and Bingöl said the firm intends to have its wheeled loaders
  • Euro Auctions is expanding its global operations with new acquisition
    January 6, 2017
    Euro Auctions is revealing its expansion plans for 2013 with the addition of a new site to its operations. Based in Dromore, Northern Ireland, Euro Auctions has been conducting unreserved auctions of industrial equipment and construction machinery since 1998. The company has permanent auction sites in Northern Ireland, England, Germany, Spain, Australia and now the USA.