Algeria to engage Japanese government over dispute with Cojaal

The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal, In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.
January 14, 2015 Read time: 3 mins
The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal,

In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.

The East-West Highway runs along the Mediterranean area of Algeria, with the eastern section running from the province of Bourdj Bou Arreridj to the Tunisian border. The road will drastically reduce the time of up to three days to drive across northern Algeria.

Cojaal - the Consortium Japonais Pour l'Autoroute Algérienne - is a joint venture comprising five of Japan’s largest companies: Japan’s two largest contractors 2809 Kajima and 2808 Taisei, general contractors 2811 Hazama and Nishimatsu as well as the trading house 4081 Itochu.

According to %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal information from Kajima Visit www.kajima.com Website false http://www.kajima.com/news_events/special_features/vol2/vol2-1.html false false%>, Cojaal was to build a six-lane motorway with three lanes on each side, 43 bridges on the main route and three tunnels. “It is one of the largest infrastructure projects ever to be undertaken by Japanese companies outside of Japan,” Kajima said at the time of the contract award.

Completion of the entire East-West Highway was originally scheduled for 2010 and most of it is completed, except for the eastern section, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17854 0 oLinkExternal as reported Visit WH Story Page false /categories/road-highway-structures/news/work-to-restart-on-key-algerian-highway-section/ false false%> by 3260 World Highways in June. But last October, Algeria’s Minister of Public Works Abdelkader Kadi terminated the contract with Cojaal to build the eastern section’s final 84km after a part of the Djebel el Ouahch tunnel in Constantine constructed by COJAAL collapsed in January last year.

Algerian Press Service reported that Kadi said the last stretch of the eastern section will be awarded to other companies, but he gave no details of which firms stood to gain the work.

Kadi also said he was confident that a satisfactory outcome for both parties will be agreed before June. However, he noted that he was also confident that Cojaal would recognise its responsibility for the delays to work over several years and the tunnel problems.

Kadi confirmed that a 13km bypass, costing nearly $57 million, is being built to resolve traffic problems due to the collapse of the tunnel and should be operational by June.

For more information on companies in this article

Related Content

  • CTE’s European lift off
    March 27, 2013
    Since signing an exclusive licensing agreement with Genie Industries in 1987, CTE has become one of the largest European groups in the field of lifting and movement of materials. Founded in 1981, the company now has a commercial presence covering all five world continents.
  • Tsurumi launches new dewatering pump on anniversary
    February 28, 2013
    Submersible pump manufacturer Tsurumi, marking its 30th anniversary in Europe, is launching a new engine driven pumps and a life-extending kit for its products. The new diesel-driven pump (4TBA82D135) is one of Tsurumi’s biggest, and is designed to work at the most demanding dewatering and sewage applications, offering a maximum flow of 2,250litres/minute and a maximum head of 18m. Tsurumi will also introduce a set of life-extending parts for its KTV and KTVE range of lightweight aluminium pumps, saying tha
  • Sumitomo intends to boost its paver sales worldwide, as vice president international sales Ichiro Shimada explained
    January 6, 2017
    Sumitomo Construction Machinery intends to continue boosting export markets – a project that has been in hand for three years – according to vice president international sales Ichiro Shimada. “Sumitomo is dominant in Japan and we have 70% market share. But the market size is limited, maybe 400 units/year. We’re putting a lot of effort into the Chinese market,” said Shimada. Europe is another key market for Sumitomo and the firm is focussing on countries such as France, Poland and Switzerland, while it has a
  • Sumitomo intends to boost its paver sales worldwide, as vice president international sales Ichiro Shimada explained
    April 18, 2012
    Sumitomo Construction Machinery intends to continue boosting export markets – a project that has been in hand for three years – according to vice president international sales Ichiro Shimada. “Sumitomo is dominant in Japan and we have 70% market share. But the market size is limited, maybe 400 units/year. We’re putting a lot of effort into the Chinese market,” said Shimada. Europe is another key market for Sumitomo and the firm is focussing on countries such as France, Poland and Switzerland, while it has a