Algeria to engage Japanese government over dispute with Cojaal

The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal, In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.
January 14, 2015 Read time: 3 mins
The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal,

In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.

The East-West Highway runs along the Mediterranean area of Algeria, with the eastern section running from the province of Bourdj Bou Arreridj to the Tunisian border. The road will drastically reduce the time of up to three days to drive across northern Algeria.

Cojaal - the Consortium Japonais Pour l'Autoroute Algérienne - is a joint venture comprising five of Japan’s largest companies: Japan’s two largest contractors 2809 Kajima and 2808 Taisei, general contractors 2811 Hazama and Nishimatsu as well as the trading house 4081 Itochu.

According to %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal information from Kajima Visit www.kajima.com Website false http://www.kajima.com/news_events/special_features/vol2/vol2-1.html false false%>, Cojaal was to build a six-lane motorway with three lanes on each side, 43 bridges on the main route and three tunnels. “It is one of the largest infrastructure projects ever to be undertaken by Japanese companies outside of Japan,” Kajima said at the time of the contract award.

Completion of the entire East-West Highway was originally scheduled for 2010 and most of it is completed, except for the eastern section, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17854 0 oLinkExternal as reported Visit WH Story Page false /categories/road-highway-structures/news/work-to-restart-on-key-algerian-highway-section/ false false%> by 3260 World Highways in June. But last October, Algeria’s Minister of Public Works Abdelkader Kadi terminated the contract with Cojaal to build the eastern section’s final 84km after a part of the Djebel el Ouahch tunnel in Constantine constructed by COJAAL collapsed in January last year.

Algerian Press Service reported that Kadi said the last stretch of the eastern section will be awarded to other companies, but he gave no details of which firms stood to gain the work.

Kadi also said he was confident that a satisfactory outcome for both parties will be agreed before June. However, he noted that he was also confident that Cojaal would recognise its responsibility for the delays to work over several years and the tunnel problems.

Kadi confirmed that a 13km bypass, costing nearly $57 million, is being built to resolve traffic problems due to the collapse of the tunnel and should be operational by June.

For more information on companies in this article

Related Content

  • Ethiopian Roads Authority (ERA) picks Spanish, Chinese contactors
    October 22, 2014
    The Ethiopian Roads Authority (ERA) has contracted out two major road projects to Spanish and Chinese companies. China Hunan Hunda Road & Bridge Construction will build the 111.3km Merkote-Delbo junction-Alaba-Sodo road under a contract worth around US$50 million (€39.12 million). Completion is within two and a half years. Spanish joint venture UTE Elsameks Eco Asphalt Ethiopia 35 will handle the 63km Ambo-Welliso project. Completion is due in three years, with funding of around $59 million from the W
  • Eurasphalt & Eurobitume Congress 2016 in Prague calls for papers and speakers
    October 8, 2014
    The 6th Eurasphalt & Eurobitume Congress, which is being organised by EAPA & Eurobitume in Prague in the Czech Republic on June 1 to 3 2016, has put out a call for papers. Speakers and authors should submit their abstracts online say the Eurasphalt & Eurobitume Congress 2016 organisers and all papers submitted will receive DOI (Digital Object Identifier) indexation. The organisers say that they “recognise the trend towards online availability of publications and it is the intention to index the proceeding
  • VIDEO: Rollerman Blondeau takes to the hills, Grimsel Pass
    July 26, 2016
    Sure, it’s a spectacular run down a mountain road. But it’s also an extremely visual reminder that highway infrastructure is important for work and play. Let’s not forget that the road - in this case Switzerland’s Grimsel Pass, 2,164m - has to be smooth enough for Jean Yves “Rollerman” Blondeau to reach those speeds without being chucked over edge and down a cliff. The pass is a driver’s delight as it crosses the continental divide in the Alps where rivers flow one way towards the North Sea and the ot
  • Hitachi to place “greater emphasis” on local production focus – HCME president
    January 6, 2017
    Moriaki Kadoya, president and chief executive of Hitachi Construction Machinery Europe (HCME), says Hitachi Construction Machinery needs to place “greater emphasis” on establishing local production facilities as it bids to strengthen its market position. A subsidiary of the Hitachi Group, Hitachi Construction Machinery currently has 33 production sites worldwide – with 16, including its flagship production site near Tokyo, in Japan.