Algeria to engage Japanese government over dispute with Cojaal

The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal, In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.
January 14, 2015 Read time: 3 mins
The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal,

In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.

The East-West Highway runs along the Mediterranean area of Algeria, with the eastern section running from the province of Bourdj Bou Arreridj to the Tunisian border. The road will drastically reduce the time of up to three days to drive across northern Algeria.

Cojaal - the Consortium Japonais Pour l'Autoroute Algérienne - is a joint venture comprising five of Japan’s largest companies: Japan’s two largest contractors 2809 Kajima and 2808 Taisei, general contractors 2811 Hazama and Nishimatsu as well as the trading house 4081 Itochu.

According to %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal information from Kajima Visit www.kajima.com Website false http://www.kajima.com/news_events/special_features/vol2/vol2-1.html false false%>, Cojaal was to build a six-lane motorway with three lanes on each side, 43 bridges on the main route and three tunnels. “It is one of the largest infrastructure projects ever to be undertaken by Japanese companies outside of Japan,” Kajima said at the time of the contract award.

Completion of the entire East-West Highway was originally scheduled for 2010 and most of it is completed, except for the eastern section, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 17854 0 oLinkExternal as reported Visit WH Story Page false /categories/road-highway-structures/news/work-to-restart-on-key-algerian-highway-section/ false false%> by 3260 World Highways in June. But last October, Algeria’s Minister of Public Works Abdelkader Kadi terminated the contract with Cojaal to build the eastern section’s final 84km after a part of the Djebel el Ouahch tunnel in Constantine constructed by COJAAL collapsed in January last year.

Algerian Press Service reported that Kadi said the last stretch of the eastern section will be awarded to other companies, but he gave no details of which firms stood to gain the work.

Kadi also said he was confident that a satisfactory outcome for both parties will be agreed before June. However, he noted that he was also confident that Cojaal would recognise its responsibility for the delays to work over several years and the tunnel problems.

Kadi confirmed that a 13km bypass, costing nearly $57 million, is being built to resolve traffic problems due to the collapse of the tunnel and should be operational by June.

For more information on companies in this article

Related Content

  • Losing your car ain’t as hard as you would think
    April 29, 2015
    Thankfully it doesn’t happen too often, but forgetting where you parked your car can be an embarrassing moment, or several days, as one man in the UK recently found. Jason Matthews, 40, ran the Manchester City Marathon on April 19 in five hours and 11 minutes and then spent an additional several hours looking for his Saab 93 Sport. He said he couldn’t recall where he had parked the vehicle. He walked back around some of the 26-mile – nearly 42km - course, before driving around in a taxi for 40 minutes an
  • Bauma 2016 Innovation Awards entries accepted starting today
    April 1, 2015
    Entries are now open for the bauma Innovation Awards to be presented at the international construction and construction equipment trade fair bauma in Munich in 2016. As last time, in 2016 the awards are again being presented in five categories: • Machinery • Components • Construction process/Construction work • Research • Design bauma 2016 in Munich is a major international showcase for construction machinery, building material machines, mining machines, construction vehicles and c
  • Atlas dealers to add Effer cranes to their range
    January 6, 2017
    Crane dealers across the Atlas network will be able to add Effer cranes to the range of products they offer. Effer cranes will be sold, serviced and supported by Atlas dealers in different countries and particularly in Germany and the Middle East. The Atlas display at bauma features a new Atlas AK 955, built by Effer with Atlas colours and branding. Effer and Atlas began working together in the UK market in 2012. Success of the cooperation has led to its expansion worldwide. Atlas’s owner, Fil Filipov, said
  • Atlas dealers to add Effer cranes to their range
    April 15, 2013
    Crane dealers across the Atlas network will be able to add Effer cranes to the range of products they offer. Effer cranes will be sold, serviced and supported by Atlas dealers in different countries and particularly in Germany and the Middle East. The Atlas display at bauma features a new Atlas AK 955, built by Effer with Atlas colours and branding. Effer and Atlas began working together in the UK market in 2012. Success of the cooperation has led to its expansion worldwide. Atlas’s owner, Fil Filipov, said