Vietnam’s North-South Expressway project prioritised

Vietnam’s Ministry of Transport is prioritising the construction of the North-South expressway project. It is seeking the approval of the Vietnamese Government approval to speed up the development of a 713km stretch of the expressway. This particular section of the expressway is phase one of the project and has an estimated construction cost of US$ 5.73 billion. Just over half of the construction cost will be paid for by private investors while Government bonds are expected to pay for the remaining sum. Thi
October 20, 2017 Read time: 2 mins
Vietnam’s Ministry of Transport is prioritising the construction of the North-South expressway project. It is seeking the approval of the 983 Vietnamese Government approval to speed up the development of a 713km stretch of the expressway. This particular section of the expressway is phase one of the project and has an estimated construction cost of US$ 5.73 billion. Just over half of the construction cost will be paid for by private investors while Government bonds are expected to pay for the remaining sum. This first stretch of the expressway will connect the provinces of Dong Nai, Khanh Hoa, Hue, Quang Tri, Ha Tinh and Nam Dinh, with work being carried out from 2017 to 2020. The 713km section is being split into 11 separate construction deals, eight of which will be under the build-operate-transfer model and three utilising public funding.


Work on the second phase of the expressway will be carried out from 2020 to 2025 and will include sections from Bai Vot in Ha Tinh to Cam Lo in Quang Tri, and from Quang Ngai to Nha Trang. This second phase will be split into nine separate contracts. The first two phases will measure 1,372km and will cost $13.75 billion to build.

The third phase of the work will be for the stretch from Can Tho to Ca Mau and work will start in 2025. In all the expressway will measure 2,109km long and will run from Lang Son province in the north of Vietnam to Ca Mau province in the south of the country. The expressway project will include upgrading some existing sections of the route, with widening and improvement work and increasing the number of lanes from two to four. The project will also include the construction of new sections of four lane expressway however. Once complete the new expressway will cut journey times and improve transport right across the country.

For more information on companies in this article

Related Content

  • Work commencing on Vietnam’s key road building project
    September 5, 2019
    Work is starting on a section of the road that will connect Son La and Cam Lo in Vietnam.
  • Zimbabwe highway project linking with its neighbours
    November 28, 2016
    Zimbabwe’s Beitbridge to Chirundu highway link now looks set for a complete upgrade. The project has been planned for over 10 years but has faced a series of setbacks and delays, with funding having proved one of the biggest stumbling blocks in the past. The 897km highway runs from Beitbridge, located on the border with South Africa in the south of Zimbabwe all the way up to Chirundu, which is just over the border with Zambia in the north. The route includes part of the A4 highway in the south and the A1 hi
  • Highway widening project for the US
    April 19, 2018
    A highway widening project in the US state of New Hampshire is being assisted by the use of a gravity-fed asphalt paver. The widening work is being carried out as part of an upgrade for a 32km stretch of I-93, which was started eight years ago. The work is being carried out for the New Hampshire Department of Transportation (NHDOT) on a section of the highway between Exits 1 and 5 from the Massachusetts Stateline to Manchester, NH. According to NHDOT, the project involves widening I-93 from two lanes in
  • Sri Lanka benefiting from external highway investment
    July 16, 2013
    Key highway projects in Sri Lanka are now moving forward. Chinese investment will finance a new tolled highway in Sri Lanka. The project for the US$1.5 billion tolled highway is being handled jointly by China Merchants Hua Jian Highway Investment Company and China Merchants Holdings (International) Company. The agreement is to build and operate the highway over a 25-30 year period, and which will be constructed in four separate phases. The first phase will be from Enderamulla to Ambepussa, with the second f