Vietnam’s North-South Expressway project prioritised

Vietnam’s Ministry of Transport is prioritising the construction of the North-South expressway project. It is seeking the approval of the Vietnamese Government approval to speed up the development of a 713km stretch of the expressway. This particular section of the expressway is phase one of the project and has an estimated construction cost of US$ 5.73 billion. Just over half of the construction cost will be paid for by private investors while Government bonds are expected to pay for the remaining sum. Thi
October 20, 2017 Read time: 2 mins
Vietnam’s Ministry of Transport is prioritising the construction of the North-South expressway project. It is seeking the approval of the 983 Vietnamese Government approval to speed up the development of a 713km stretch of the expressway. This particular section of the expressway is phase one of the project and has an estimated construction cost of US$ 5.73 billion. Just over half of the construction cost will be paid for by private investors while Government bonds are expected to pay for the remaining sum. This first stretch of the expressway will connect the provinces of Dong Nai, Khanh Hoa, Hue, Quang Tri, Ha Tinh and Nam Dinh, with work being carried out from 2017 to 2020. The 713km section is being split into 11 separate construction deals, eight of which will be under the build-operate-transfer model and three utilising public funding.


Work on the second phase of the expressway will be carried out from 2020 to 2025 and will include sections from Bai Vot in Ha Tinh to Cam Lo in Quang Tri, and from Quang Ngai to Nha Trang. This second phase will be split into nine separate contracts. The first two phases will measure 1,372km and will cost $13.75 billion to build.

The third phase of the work will be for the stretch from Can Tho to Ca Mau and work will start in 2025. In all the expressway will measure 2,109km long and will run from Lang Son province in the north of Vietnam to Ca Mau province in the south of the country. The expressway project will include upgrading some existing sections of the route, with widening and improvement work and increasing the number of lanes from two to four. The project will also include the construction of new sections of four lane expressway however. Once complete the new expressway will cut journey times and improve transport right across the country.

For more information on companies in this article

Related Content

  • Vietnam province to spend US$2.77bn on transport infrastructure over next 8 years
    April 24, 2012
    Long An province in Vietnam will see US$2.77billion spent on constructing and improving its inner waterway and road infrastructure over the next eight years. The provincial peoples’ committee (PPC) revealed that the major capital project will include the construction of bridges and roads linking central areas and towns. The new roads will stretch around 400km and new dredge waterways will span 600km on the Chanh, Thu Thua, Bac Dong and Tra Cu canals by 2015. Small wharves and Long An Port will also be estab
  • Vietnam’s key highway project feasibility study
    March 9, 2018
    The feasibility study is being handled for a stretch of Vietnam’s North-South highway project. The project is likely to cost US$5.22 billion, of which $2.8 billion will be provided by private funding sources, with the remainder coming from the Vietnamese Government’s sources. The project is being overseen by Vietnam’s Ministry of Transport. Vietnam’s Department of Public-Private Partnership (PPP) Projects has urged the bodies involved with eight PPP sub-projects to complete feasibility studies for these
  • Vietnam’s key highway project commencing
    February 14, 2019
    Construction of Vietnam’s North-South expressway is planned to commence during 2019. An initial funding package of US$600 million will pay for the start of the works, which includes buying the land and clearing the way for the route. The winners of the tenders for the first sections should be announced in April-June 2019, with these sections due for completion in 2021. The winners of the tenders for a bridge section on the route should be announced in October 2019, with the bridge due for completion in 2022
  • US$4 billion for road expansion in Vietnam
    May 21, 2024
    US$4 billion investment is planned for road expansion in Vietnam.