Vietnam highway construction project facing halt

A Vietnam highway construction project is facing a halt to works.
By MJ Woof March 5, 2020 Read time: 1 min
Work is being halted on an important expressway project in Vietnam – image © courtesy of Marko Bukorovic, Dreamstime.com

Work may be halted on the Ben Luc-Long Thanh expressway project in Vietnam. The problem is that the construction costs have increased over the original budget. Building the expressway is now expected to cost US$70 million more than had been originally planned.

The Vietnam Expressway Corporation (VEC) has proposed halting the work due to the extra costs, which relate to two portions of the project.

The original cost for the Ben Luc-Long Thanh expressway project was $1.34 billion and the work is currently 76% complete. However, building the Phuoc Khanh bridge is costing $38 million while the construction of the Binh Khanh bridge is costing $32 million.

Much of the funding for the expressway project is being provided by the Asian Development Bank and the Japan International Cooperation Agency. However, a new financing approach will be required for the project to be completed.

Related Content

  • Vietnam highway project completed by OHL
    September 7, 2017
    Work is now complete on the US$76.3 million highway project providing a key link between the North and the South of Vietnam at Da Nang city. This 13km project was carried out by Spanish contractor OHL, having been awarded in 2014 by Vietnam Expressway Corporation. Financing for the work came from the Japan International Cooperation Agency (JICA). Meanwhile OHL is also building a 544m viaduct over the Lanch Tray River in Vietnam that will provide a new link to the coastal city of Hai Phong.
  • Vietnam’s US$1.1 billion expressway stretch
    April 19, 2024
    New additions are planned for Vietnam’s US$1.1 billion expressway project.
  • Vietnam’s massive expressway expansion
    March 6, 2025
    Vietnam is working on a massive expansion of its expressway network.
  • Vietnam bridge, road and highway development projects
    June 20, 2018
    Vietnam is pushing ahead with a series of road, highway and bridge projects that will improve the country’s transport network. Feasibility studies for three stretches of the North-South Expressway have been received by Vietnam’s Ministry of Transport (MoT). The 29km stretch from Nha Trang to Cam Lam is expected to cost US$177.9 million, with work starting in 2019 and due for completion in 2021. The 60km stretch from Dau Giay to Tan Phu will be built from 2018 to 2022. The 101km stretch from Vinh Hao to Pha